 Projects — TIB Project Information

TIB Project Information

City of Vancouver's SE McGillivray Blvd

P-W-184(P11)-1

P-W-184(P11)-1
SE McGillivray Blvd

Chkalov Dr to 164th Ave

FY 2026 Active Transportation Program
Current Phase : Design
Total TIB Funding : $700,000

County: Clark   |   Legislative District: 17   |   Project Length: 2.60   |   TIB Engineer: Chris Langhoff   |   Last Payment Date:

Project Information

Lead Agency VANCOUVER
Funding Year 2026
Program ATP
Current Phase Design
Legislative District 17
Congressional District 3
Federal Route Number 4234
Project Length 2.60 mi.
ADT 10,836
Functional Class Minor
Type of Work Pedestrian
Project Contact Emily Benoit
Contact Email emily.benoit@cityofvancouver.us
TIB Engineer Chris Langhoff
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 12/30/2024 01/06/2025
Bid Auth. Approval 12/15/2025
Construction Approval 03/01/2026
Project Closeout 12/31/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 86,697 258,725
Right of Way 0 0
Total Design 86,697 258,725
     
Construction Engineering 79,995 238,725
Construction Contract 533,308 1,591,525
Other Construction 0 0
Total Construction 613,303 1,830,250
     
Total TIB Funding 700,000 2,088,975

Local Funding Partners

Funding Amount Percent
VANCOUVER 1,388,975 66.5%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 1,388,975 66.5%

Project Description

This project will repurpose existing right-of-way in coordination with the pavement management program to create a more balanced roadway that provides and enhances dedicated space for people biking and walking while improving safety for all modes.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments