The existing sidewalk ends on Highway 99 just south of the Tenny Creek crossing. Highway 99 is a four-lane principal arterial paralleling lnterstate-5 between downtown Vancouver and NE 134th Street and is one of the highest accident corridors in Clark County.
Projects — TIB Project Information
TIB Project Information
Clark County's Highway 99 Sidewalk
P-W-006(P12)-1
P-W-006(P12)-1
Highway 99 Sidewalk
NE 102nd St NE 104th St
FY 2026 Active Transportation Program
Current Phase : Design
Total TIB Funding : $500,001
County: Clark | Legislative District: 18 | Project Length: 500.00 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
Lead Agency | CLARK COUNTY |
Funding Year | 2026 |
Program | ATP |
Current Phase | Design |
Legislative District | 18 |
Congressional District | 3 |
Federal Route Number | 4253 |
Project Length | 500.00 mi. |
ADT | 13,749 |
Functional Class | Principal |
Type of Work | Pedestrian |
Project Contact | Laura Hoggatt |
Contact Email | Laura.Hoggatt@clark.wa.gov |
TIB Engineer | Chris Langhoff |
Last Payment Date | |
Cultural Resource Assessment | Section 106 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 03/01/2025 | 02/05/2025 |
Bid Auth. Approval | 04/30/2025 | |
Construction Approval | 05/30/2025 | |
Project Closeout | 12/31/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 73,301 | 179,000 |
Construction Contract | 420,557 | 1,027,000 |
Other Construction | 6,143 | 15,000 |
Total Construction | 500,001 | 1,221,000 |
Total TIB Funding | 500,001 | 1,221,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
CLARK COUNTY | 70,999 | 5.8% |
WSDOT Funding | 0 | 0.0% |
Transportation Alternatives FHWA | 650,000 | 53.2% |
Total Local Funding | 720,999 | 59.0% |
Project Description
This project will construct new raised concrete curb and sidewalk on the east side of Highway 99 and south side of NE 104th Street.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Removes ADA barriers
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |