There is an existing gap in sidewalk between the existing Fryelands Boulevard walking trail and the concrete sidewalk on Main Street. There is also not a crosswalk between the northwest corner of the intersection and the south side of Main Street. This walking path acts as pedestrian connection to an existing coffee stand, and also provides pedestrian access to the High School.
Projects — TIB Project Information
TIB Project Information
City of Monroe's Freylands Blvd and Main Street Sidewalk
P-P-822(P05)-1
P-P-822(P05)-1
Freylands Blvd and Main Street Sidewalk
Fryelands Bvld to Main St Roundabout
FY 2026 Active Transportation Program
Current Phase : Design
Total TIB Funding : $269,000
County: Snohomish | Legislative District: 12 | Project Length: 380.00 | TIB Engineer: Greg Armstrong | Last Payment Date:
Project Information
Lead Agency | MONROE |
Funding Year | 2026 |
Program | ATP |
Current Phase | Design |
Legislative District | 12 |
Congressional District | 1 |
Federal Route Number | 2630 |
Project Length | 380.00 mi. |
ADT | 10,000 |
Functional Class | Minor |
Type of Work | Pedestrian |
Project Contact | Derek Hann |
Contact Email | dhann@monroewa.gov |
TIB Engineer | Greg Armstrong |
Last Payment Date | |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | 01/08/2025 | |
Predesign Approval | ||
Design Approval | 02/01/2025 | 12/18/2024 |
Bid Auth. Approval | 03/01/2026 | |
Construction Approval | 05/14/2026 | |
Project Closeout | 12/31/2026 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 55,628 | 70,000 |
Right of Way | 0 | 0 |
Total Design | 55,628 | 70,000 |
Construction Engineering | 7,788 | 9,800 |
Construction Contract | 205,584 | 258,700 |
Other Construction | 0 | 0 |
Total Construction | 213,372 | 268,500 |
Total TIB Funding | 269,000 | 338,500 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MONROE | 69,500 | 20.5% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 69,500 | 20.5% |
Project Description
This project will construct 380 linear feet of sidewalk, planter strip and curb and gutter will close the gap along Main Street. This work will also require some minor drainage modification with the construction of two catchbasins and a retaining wall approximately 5 feet in height along approximately 100 linear feet of the project.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Completes gap;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |