Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Monroe's RRFB Crossings

P-P-822(P04)-1

P-P-822(P04)-1
RRFB Crossings

Multiple Locations

FY 2026 Active Transportation Program
Current Phase : Construction
Total TIB Funding : $70,090

County: Snohomish   |   Legislative District: 12   |   Project Length: 1.00   |   TIB Engineer: Greg Armstrong   |   Last Payment Date:

Project Information

Lead Agency MONROE
Funding Year 2026
Program ATP
Current Phase Construction
Legislative District 12
Congressional District 1
Federal Route Number 2630
Project Length 1.00 mi.
ADT 10,000
Functional Class Minor
Type of Work Pedestrian
Project Contact Derek Hann
Contact Email dhann@monroewa.gov
TIB Engineer Greg Armstrong
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2025 12/18/2024
Bid Auth. Approval 05/01/2025 01/15/2025
Construction Approval 07/01/2025 01/16/2025
Project Closeout 10/31/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 11,760 14,700
Right of Way 0 0
Total Design 11,760 14,700
     
Construction Engineering 2,240 2,800
Construction Contract 56,090 61,024
Other Construction 0 9,089
Total Construction 58,330 72,913
     
Total TIB Funding 70,090 87,613

Local Funding Partners

Funding Amount Percent
MONROE 17,523 20.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 17,523 20.0%

Project Description

The project will add four RRFBs enhanced crossings. One of the proposed crossings will require three beacons, as there is an existing median on a four-lane road section. Three crossings will only require two beacons, as the roadway is narrower with two-lanes. The City plans to utilize local agency forces to perform the design and construction. The funding request from TIB will be used in support of the construction phase only. There are four locations that we are looking at -2 beacons at the intersection of Blueberry and King -3 beacons at Main and Sams -2 beacons at the Lewis and Fremont -2 beacons at Chain Lake Road

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments