TIB Project Information
Town of Carbonado's 7th Street Sidewalk
P-P-809(P02)-1
P-P-809(P02)-1
7th Street Sidewalk
OFerrell Dr to Wingate Dr
FY 2024 Active Transportation Program
Current Phase : Audit
Total TIB Funding : $187,168
County: Pierce | Legislative District: 31 | Project Length: 200.00 | TIB Engineer: Greg Armstrong | Last Payment Date: 09/11/2024
Project Information
Lead Agency | CARBONADO |
Funding Year | 2024 |
Program | ATP |
Current Phase | Audit |
Legislative District | 31 |
Congressional District | 8 |
Federal Route Number | 9999 |
Project Length | 200.00 mi. |
ADT | 150 |
Functional Class | TIB Arterial |
Type of Work | Pedestrian |
Project Contact | Sandi Carlson |
Contact Email | clerk@carbonado.org |
TIB Engineer | Greg Armstrong |
Last Payment Date | 09/11/2024 |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | 03/20/2017 | |
Predesign Approval | ||
Design Approval | 02/01/2023 | 01/11/2023 |
Bid Auth. Approval | 02/29/2024 | 01/30/2024 |
Construction Approval | 03/12/2024 | 04/29/2024 |
Project Closeout | 08/30/2024 | 09/10/2024 |
Audit Date | 09/11/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 31,635 | 33,210 |
Right of Way | 0 | 0 |
Total Design | 31,635 | 33,210 |
Construction Engineering | 31,635 | 14,795 |
Construction Contract | 211,242 | 152,161 |
Other Construction | 0 | 0 |
Total Construction | 242,877 | 166,956 |
Funding Increase | 2,321 | |
Funding Surplus | - 89,665 | |
Total TIB Funding | 187,168 | 200,166 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
CARBONADO | 12,998 | 6.5% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 12,998 | 6.5% |
Project Description
This project will install sidewalk on the north side of 7th Street to close the gap in the sidewalk system utilizing the existing ramps installed on OFerrell Drive and Wingate Drive.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Completes gap;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |