City of North Bend's SR202 Sidewalk Gap

P-P-804(P09)-1

P-P-804(P09)-1
SR202 Sidewalk Gap

North Bend Way to RR Tracks

FY 2025 Active Transportation Program
Current Phase : Audit
Total TIB Funding : $154,917

County: King   |   Legislative District: 12   |   Project Length: 110.00   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 11/26/2025

Project Information

Lead Agency NORTH BEND
Funding Year 2025
Program ATP
Current Phase Audit
Legislative District 12
Congressional District 8
Federal Route Number 0202
Project Length 110.00 mi.
ADT 15,000
Functional Class Minor
Type of Work Pedestrian
Project Contact Dan Marcinko
Contact Email dmarcinko@northbendwa.gov
TIB Engineer Greg Armstrong
Last Payment Date 11/26/2025
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
DAHP Assessment Date   10/11/2024
Predesign Approval
Design Approval 02/08/2024 02/05/2024
Bid Auth. Approval 11/01/2024 10/11/2024
Construction Approval 02/28/2025 02/26/2025
Project Closeout 11/12/2025 11/17/2025
Audit Date   11/26/2025
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 15,440 79,695
Right of Way 0 0
Total Design 15,440 79,695
     
Construction Engineering 15,440 17,304
Construction Contract 102,939 146,132
Other Construction 0 0
Total Construction 118,379 163,436
     
Funding Increase 29,462  
Funding Surplus - 8,364  
Total TIB Funding 154,917 243,131

Local Funding Partners

Funding Amount Percent
NORTH BEND 88,214 36.3%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 88,214 36.3%

Project Description

This project replaces the existing narrow sidewalk along SR 202 between North Bend Way and the RR Tracks with an ADA compliant 8-foot sidewalk, curb and gutter.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.