TIB Project Information

City of Duvall's Main Street (SR 203) / Cherry Street RRFB

P-P-802(P03)-1

P-P-802(P03)-1
Main Street (SR 203) / Cherry Street RRFB

NE Cherry St Crossing

FY 2025 Active Transportation Program
Current Phase : Audit
Total TIB Funding : $91,215

County: King   |   Legislative District: 45   |   Project Length: 70.00   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 12/30/2024

Project Information

Lead Agency DUVALL
Funding Year 2025
Program ATP
Current Phase Audit
Legislative District 45
Congressional District 8
Federal Route Number 0203
Project Length 70.00 mi.
ADT 12,000
Functional Class Minor
Type of Work Pedestrian
Project Contact Ben Ressler
Contact Email benjamin.ressler@duvallwa.gov
TIB Engineer Greg Armstrong
Last Payment Date 12/30/2024
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 01/01/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 01/01/2024 12/06/2023
Bid Auth. Approval 02/29/2024 02/22/2024
Construction Approval 03/20/2024 03/25/2024
Project Closeout 12/31/2024 12/16/2024
Audit Date   12/30/2024
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 5,100 0
Construction Contract 62,730 77,668
Other Construction 0 29,730
Total Construction 67,830 107,398
     
Funding Increase 28,448  
Funding Surplus - 5,063  
Total TIB Funding 91,215 107,398

Local Funding Partners

Funding Amount Percent
DUVALL 16,183 15.1%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 16,183 15.1%

Project Description

This project installs a solar powered RRFB crossing system across the northernmost intersection of SR-203 and NE Cherry Street. Adding this system (poles, audible buttons, signage, lighting, panels)

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments