The Riverview School District / Cherry Valley Elementary School has reached out the City multiple times about improving the school crossing at 3rd Avenue NE and NE 163rd St. Children use this crossing is the primary entrance to Cherry Valley Elementary before and after school and we have been informed by the school that people often fail to stop at the crosswalk. This is likely due the sharp curvature of 3rd Avenue heading South, causing a sight distance issue to the crosswalk.
Projects — TIB Project Information
TIB Project Information
City of Duvall's 3rd Avenue School Crossing Improvement
P-P-802(P05)-1
P-P-802(P05)-1
3rd Avenue School Crossing Improvement
NE 163rd St Intersection
FY 2026 Active Transportation Program
Current Phase : Bid Authorization
Total TIB Funding : $42,500
County: King | Legislative District: 45 | Project Length: 50.00 | TIB Engineer: Greg Armstrong | Last Payment Date:
Project Information
Lead Agency | DUVALL |
Funding Year | 2026 |
Program | ATP |
Current Phase | Bid Authorization |
Legislative District | 45 |
Congressional District | 8 |
Federal Route Number | 2273 |
Project Length | 50.00 mi. |
ADT | 1,350 |
Functional Class | Collector |
Type of Work | |
Project Contact | Benjamin Ressler |
Contact Email | benjamin.ressler@duvallwa.gov |
TIB Engineer | Greg Armstrong |
Last Payment Date | |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 01/01/2026 | |
DAHP Assessment Date | 01/02/2025 | |
Predesign Approval | ||
Design Approval | 12/01/2024 | 12/03/2024 |
Bid Auth. Approval | 03/07/2025 | 03/04/2025 |
Construction Approval | 04/23/2025 | |
Project Closeout | 10/31/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 32,300 | 38,000 |
Other Construction | 10,200 | 12,000 |
Total Construction | 42,500 | 50,000 |
Total TIB Funding | 42,500 | 50,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
DUVALL | 7,500 | 15.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 7,500 | 15.0% |
Project Description
The project adds RRFBs at the intersection and an additional RRFB on 3rd Avenue NE North of the intersection around the blind curve. This will allow for drivers approaching the intersection to be aware of the pedestrians crossing before they can even see the intersection. Additionally, we are proposing retrofitting the curb ramp at the southeast corner and adding a curb extension to reduce the crossing length and narrow 3rd Avenue NE.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Provides traffic calming;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |