The proposed project is one of two remaining segments for the non-motorized connection between I-5 and the north portion of the City of Lakewood, tying to the Oakbrook neighborhood community located at the northern boundary city limits. The second of the two segments is another proposed project that extends this Interlaaken Drive Sidewalk project west and north along 112th St SW and Idlewild Rd SW, respectively. The City has recently completed the Washington Boulevard and Gravelly Lake Drive projects, which originate from I-5, and is currently completing the Hipkins Rd SW street improvement project which provides connection north to Steilacoom Blvd. Existing conditions within the corridor include two lanes and walking paths where shoulders are available. However, there are large sections of Interlaaken Drive where there is no available shoulder and pedestrians are left no choice but to walk along the road. Bicyclists are also challenged by existing 11 travel lanes without shoulders.
Projects — TIB Project Information
TIB Project Information
City of Lakewood's Interlaaken Drive Sidewalk
P-P-199(P12)-1
P-P-199(P12)-1
Interlaaken Drive Sidewalk
Washington Blvd to 112th St
FY 2026 Active Transportation Program
Current Phase : Bid Authorization
Total TIB Funding : $500,000
County: Pierce | Legislative District: 28 | Project Length: 2,410.00 | TIB Engineer: Greg Armstrong | Last Payment Date:
Project Information
Lead Agency | LAKEWOOD |
Funding Year | 2026 |
Program | ATP |
Current Phase | Bid Authorization |
Legislative District | 28 |
Congressional District | 10 |
Federal Route Number | 2917 |
Project Length | 2410.00 mi. |
ADT | 2,660 |
Functional Class | Collector |
Type of Work | Pedestrian |
Project Contact | Troy Pokswinski |
Contact Email | tpokswinski@cityoflakewood.us |
TIB Engineer | Greg Armstrong |
Last Payment Date | |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 01/01/2026 | |
DAHP Assessment Date | 02/13/2025 | |
Predesign Approval | ||
Design Approval | 02/01/2025 | 12/03/2024 |
Bid Auth. Approval | 04/10/2025 | 04/15/2025 |
Construction Approval | 05/01/2025 | |
Project Closeout | 08/31/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 31,332 | 120,000 |
Construction Contract | 468,668 | 1,795,000 |
Other Construction | 0 | 0 |
Total Construction | 500,000 | 1,915,000 |
Total TIB Funding | 500,000 | 1,915,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
LAKEWOOD | 1,415,000 | 73.9% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 1,415,000 | 73.9% |
Project Description
This project will include complete street elements by constructing new curbs, gutter, and sidewalks on both sides, repaving the existing wearing course, bringing streetlighting up to design standards, and replacing storm drainage. Non-motorized travel will be available through the central section of the City from the south to the north city limits which includes direct access to an elementary school (Idlewild) and high school (Lakes).
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Completes gap;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |