 Projects — TIB Project Information

TIB Project Information

City of Brier's RRFB Installation

P-P-144(P03)-1

P-P-144(P03)-1
RRFB Installation

Multiple Locations

FY 2026 Active Transportation Program
Current Phase : Bid Authorization
Total TIB Funding : $74,218

County: Snohomish   |   Legislative District: 1   |   Project Length: 120.00   |   TIB Engineer: Greg Armstrong   |   Last Payment Date:

Project Information

Lead Agency BRIER
Funding Year 2026
Program ATP
Current Phase Bid Authorization
Legislative District 1
Congressional District 1
Federal Route Number 2529
Project Length 120.00 mi.
ADT 0
Functional Class Collector
Type of Work
Project Contact John Forba
Contact Email johnf@paceengrs.com
TIB Engineer Greg Armstrong
Last Payment Date
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date   03/26/2025
Predesign Approval
Design Approval 01/15/2025 01/15/2025
Bid Auth. Approval 04/21/2025 04/19/2025
Construction Approval 05/01/2025
Project Closeout 07/01/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 5,546 6,525
Right of Way 0 0
Total Design 5,546 6,525
     
Construction Engineering 8,959 10,540
Construction Contract 59,713 70,250
Other Construction 0 0
Total Construction 68,672 80,790
     
Total TIB Funding 74,218 87,315

Local Funding Partners

Funding Amount Percent
BRIER 13,097 15.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 13,097 15.0%

Project Description

Upgrade the current flashing beacons with the current standards and performance requirements as this will result in brighter RRTB. The existing poles will be utilized but new signage, hardware and appurtenances will be installed. In addition it is proposed that 2 advanced warning signs will be installed at a location approximately 100-125 feet before the crosswalk at Poplar Way and 216th. This would require two new poles to be installed as well as the new signage, hardware and appurtenances.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments