Pedestrians currently walk in the the parking lanes along Algona Boulevard N.
Projects — TIB Project Information
TIB Project Information
City of Algona's Algona Boulevard N
P-P-119(P02)-1
P-P-119(P02)-1
Algona Boulevard N
Boundary Rd to S 5th St
FY 2026 Active Transportation Program
Current Phase : Design
Total TIB Funding : $545,058
County: King | Legislative District: 30 | Project Length: 1.35 | TIB Engineer: Greg Armstrong | Last Payment Date:
Project Information
Lead Agency | ALGONA |
Funding Year | 2026 |
Program | ATP |
Current Phase | Design |
Legislative District | 30 |
Congressional District | 9 |
Federal Route Number | 9999 |
Project Length | 1.35 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Pedestrian |
Project Contact | Jessica Griess |
Contact Email | jessicag@algonawa.gov |
TIB Engineer | Greg Armstrong |
Last Payment Date | |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/11/2025 | 02/13/2025 |
Bid Auth. Approval | 05/12/2025 | |
Construction Approval | 06/10/2025 | |
Project Closeout | 12/12/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 52,749 | 58,610 |
Right of Way | 0 | 0 |
Total Design | 52,749 | 58,610 |
Construction Engineering | 52,749 | 58,610 |
Construction Contract | 439,560 | 488,400 |
Other Construction | 0 | 0 |
Total Construction | 492,309 | 547,010 |
Total TIB Funding | 545,058 | 605,620 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
ALGONA | 60,562 | 10.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 60,562 | 10.0% |
Project Description
Algona Boulevard between Boundary Rd and S 5th St will be reconfigured with a separated non-motorized facility along the west side, narrower travel lanes and parking along along the east side.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Completes gap;
- Removes ADA barriers;
- Builds multimodal facilities
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |