City of Kirkland's Pedestrian Crossing at Lake Washington Institute of Technology

P-P-111(P08)-1

P-P-111(P08)-1
Pedestrian Crossing at Lake Washington Institute of Technology

132nd Ave NE

FY 2025 Active Transportation Program
Current Phase : Construction
Total TIB Funding : $131,355

County: King   |   Legislative District: 45   |   Project Length: 40.00   |   TIB Engineer: Greg Armstrong   |   Last Payment Date:

Project Information

Lead Agency KIRKLAND
Funding Year 2025
Program ATP
Current Phase Construction
Legislative District 45
Congressional District 1
Federal Route Number 2067
Project Length 40.00 mi.
ADT 6,758
Functional Class Minor
Type of Work Pedestrian
Project Contact Ling Wang-Staley
Contact Email lwangstaley@kirklandwa.gov
TIB Engineer Greg Armstrong
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2024 01/24/2024
Bid Auth. Approval 01/31/2025 01/24/2024
Construction Approval 01/31/2025 12/31/2024
Project Closeout 12/31/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 35,866 22,330
Right of Way 0 0
Total Design 35,866 22,330
     
Construction Engineering 35,715 0
Construction Contract 193,419 152,000
Other Construction 0 0
Total Construction 229,134 152,000
     
Funding Surplus - 133,645  
Total TIB Funding 131,355 174,330

Local Funding Partners

Funding Amount Percent
KIRKLAND 42,975 24.7%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 42,975 24.7%

Project Description

The project includes upgrading the current uncontrolled pedestrian crossing with the addition of a Rectangular Rapid Flashing Beacon (RRFB) pedestrian crossing at Lake Washington Institute of Technology on 132nd Avenue NE.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.