The city is trying to increase compliance with vehicles yielding to pedestrians. The city has identified top locations of 2-lane roadways for enhanced crossing treatments using the following criteria - higher volumes (above 10,000), higher speeds (35 and 40 MPH), crash history (if any), locations on walk routes for schools, meeting crosswalk policy, or identified in an adopted plan. Several locations have been included from a 2020 systemic project list and the 2022 Local Road Safety Plan.
Projects — TIB Project Information
TIB Project Information
City of Kent's RRFB Crossings
P-P-106(P07)-1
P-P-106(P07)-1
RRFB Crossings
Various
FY 2025 Active Transportation Program
Current Phase : Audit
Total TIB Funding : $54,868
County: King | Legislative District: 33 | Project Length: 10.00 | TIB Engineer: Greg Armstrong | Last Payment Date: 04/01/2025
Project Information
Lead Agency | KENT |
Funding Year | 2025 |
Program | ATP |
Current Phase | Audit |
Legislative District | 33, 47 |
Congressional District | 9 |
Federal Route Number | 1031 |
Project Length | 10.00 mi. |
ADT | 10,800 |
Functional Class | Minor |
Type of Work | Pedestrian |
Project Contact | David Paine |
Contact Email | dpaine@kentwa.gov |
TIB Engineer | Greg Armstrong |
Last Payment Date | 04/01/2025 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 01/01/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 01/06/2024 | 01/16/2024 |
Bid Auth. Approval | 05/15/2024 | 01/15/2024 |
Construction Approval | 06/01/2024 | 06/11/2024 |
Project Closeout | 02/28/2025 | 03/04/2025 |
Audit Date | 04/01/2025 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 23,269 | 0 |
Construction Contract | 81,192 | 73,534 |
Other Construction | 0 | 0 |
Total Construction | 104,461 | 73,534 |
Funding Surplus | - 49,593 | |
Total TIB Funding | 54,868 | 73,534 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
KENT | 18,666 | 25.4% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 18,666 | 25.4% |
Project Description
Install RRFB enhnaced cross walks at 5 locations, To accelerate the delivery of the solution, this city project will use in-house forces to install five RRFB-enhanced crosswalks at the proposed locations. The RRFB installation would be added to improvements made at each site to enhance pedestrian visibility specific to the location, such as extended curb, curb bulb out, crosswalk striping or stop bars, as appropriate. Military Road S 248th St 116th Ave SE SE 223rd Dr 116th Ave SE SE 234th St 132nd Ave SE SE 234th St 132nd Ave SE SE 278th St
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Increases access control;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |