Engagement for the Transportation Master Plan in 2019 identified this gap in the pedestrian network as a priority to be filled. 83rd Ave S provides a first-mile, last-mile link between transit along East Valley Highway (84th Ave S) and the southern segment of the Kent Manufacturing Industrial Center. According to PSRC data, there are approximately 3,000 family-wage jobs within 1-mile west of East Valley Highway for which this would be the shortest access path to transit and retail. transit sites are located just east of the proposed project on East valley Highway (84th Ave S).
Projects — TIB Project Information
TIB Project Information
City of Kent's 83rd Avenue S Sidewalk
P-P-106(P08)-1
P-P-106(P08)-1
83rd Avenue S Sidewalk
S 224th St to 700ft s/o S 224th St
FY 2026 Active Transportation Program
Current Phase : Design
Total TIB Funding : $625,600
County: King | Legislative District: 33 | Project Length: 700.00 | TIB Engineer: Greg Armstrong | Last Payment Date: 03/17/2025
Project Information
Lead Agency | KENT |
Funding Year | 2026 |
Program | ATP |
Current Phase | Design |
Legislative District | 33 |
Congressional District | 9 |
Federal Route Number | 1216 |
Project Length | 700.00 mi. |
ADT | 10,600 |
Functional Class | Minor |
Type of Work | Pedestrian |
Project Contact | David Paine |
Contact Email | dpaine@kentwa.gov |
TIB Engineer | Greg Armstrong |
Last Payment Date | 03/17/2025 |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/21/2025 | 02/24/2025 |
Bid Auth. Approval | 08/07/2025 | |
Construction Approval | 11/06/2025 | |
Project Closeout | 07/18/2026 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 64,000 | 80,000 |
Right of Way | 0 | 0 |
Total Design | 64,000 | 80,000 |
Construction Engineering | 73,600 | 92,000 |
Construction Contract | 488,000 | 610,000 |
Other Construction | 0 | 0 |
Total Construction | 561,600 | 702,000 |
Total TIB Funding | 625,600 | 782,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
KENT | 156,400 | 20.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 156,400 | 20.0% |
Project Description
The project will complete the gap in sidewalk along the west side of 83rd Avenue S by constructing about 700 feet of sidewalk in the existing right-of-way. The project will also include a concrete apron across S 224th Street and construct ADA curb ramps.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Completes gap;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |