SR 31 runs through the residential area of Metaline Falls for a distance of about 1/3 mile. There is no notification to the drivers that there is a need to reduce speeds through town, which creates a safety hazard for the residents. Currently SR 31 is posted 25 mph through town, the rest of the town network has a posted speed of 20 mph
Projects — TIB Project Information
TIB Project Information
Town of Metaline Falls's ATP Minimum Speed Feedback Signs
P-E-891(P03)-1
P-E-891(P03)-1
ATP Minimum Speed Feedback Signs
City limits both sides of SR 31
FY 2026 Active Transportation Program
Current Phase : Application
Total TIB Funding : $230,000
County: Pend Oreille | Legislative District: 7 | Project Length: 1,500.00 | TIB Engineer: Andrew Beagle | Last Payment Date:
Project Information
Lead Agency | METALINE FALLS |
Funding Year | 2026 |
Program | ATP |
Current Phase | Application |
Legislative District | 7 |
Congressional District | 5 |
Federal Route Number | 0031 |
Project Length | 1500.00 mi. |
ADT | 0 |
Functional Class | Minor |
Type of Work | Safety |
Project Contact | Edward Estrada |
Contact Email | townmetalinefalls@outlook.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 05/25/2025 | |
Bid Auth. Approval | 07/01/2025 | |
Construction Approval | 08/01/2025 | |
Project Closeout | 12/31/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 20,000 | 20,000 |
Right of Way | 0 | 0 |
Total Design | 20,000 | 20,000 |
Construction Engineering | 13,000 | 13,000 |
Construction Contract | 197,000 | 197,000 |
Other Construction | 0 | 0 |
Total Construction | 210,000 | 210,000 |
Total TIB Funding | 230,000 | 230,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
METALINE FALLS | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Speed feedback signs on both ends of the city limits. Additional signage on the local network to reinforce 20 mph speed limit throughout town, particularly around elementary school and the Cutter performing arts theater. A speed reduction will be requested for SR31 to 20 mph during design.
Existing Condition
Project Benefits
- Speed management, safety, livability.
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |