Winthrop does not have a non-vehicular traffic network through the town.
Projects — TIB Project Information
TIB Project Information
Town of Winthrop's Bridge Street Improvement Project
P-E-887(P02)-1
P-E-887(P02)-1
Bridge Street Improvement Project
Riverside Ave to Bluff St
FY 2025 Active Transportation Program
Current Phase : Construction
Total TIB Funding : $574,551
County: Okanogan | Legislative District: 7 | Project Length: 800.00 | TIB Engineer: Jesse Larson | Last Payment Date: 08/18/2026
Project Information
| Lead Agency | WINTHROP |
| Funding Year | 2025 |
| Program | ATP |
| Current Phase | Construction |
| Legislative District | 7 |
| Congressional District | 4 |
| Federal Route Number | 9999 |
| Project Length | 800.00 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Pedestrian |
| Project Contact | Jacob Gates |
| Contact Email | jacob@townofwinthrop.com |
| TIB Engineer | Jesse Larson |
| Last Payment Date | 08/18/2026 |
| Cultural Resource Assessment | CRA |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/01/2023 | |
| Delayed Project Date | 07/01/2026 | |
| DAHP Assessment Date | 07/31/2025 | |
| Predesign Approval | ||
| Design Approval | 05/01/2024 | 01/10/2024 |
| Bid Auth. Approval | 01/15/2026 | 03/13/2026 |
| Construction Approval | 04/05/2026 | 05/08/2026 |
| Project Closeout | 10/30/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 116,634 | 114,643 |
| Right of Way | 0 | 0 |
| Total Design | 116,634 | 114,643 |
| Construction Engineering | 52,868 | 58,930 |
| Construction Contract | 406,673 | 475,473 |
| Other Construction | 0 | 0 |
| Total Construction | 459,541 | 534,403 |
| Funding Surplus | - 1,624 | |
| Total TIB Funding | 574,551 | 649,046 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| WINTHROP | 74,495 | 11.5% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 74,495 | 11.5% |
Project Description
This project will connect sidewalk with two prior TIB projects, connecting sidewalks constructed on Bluff Street and Castle Ave.
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||