Many of Harringtons ADA ramps are not in compliance with national ADA standards. This application is the first phase of a two phase plan to replace the ADA ramps on the east side of the City. The sidewalks are generally in good condition.
Projects — TIB Project Information
TIB Project Information
City of Harrington's ADA Ramp Replacement
P-E-871(P01)-1
P-E-871(P01)-1
ADA Ramp Replacement
East Side of City
FY 2026 Active Transportation Program
Current Phase : Design
Total TIB Funding : $394,800
County: Lincoln | Legislative District: 9 | Project Length: 1.00 | TIB Engineer: Andrew Beagle | Last Payment Date:
Project Information
Lead Agency | HARRINGTON |
Funding Year | 2026 |
Program | ATP |
Current Phase | Design |
Legislative District | 9 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 1.00 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Pedestrian |
Project Contact | Joe Armand |
Contact Email | steven.marsh@tdhengineering.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 12/01/2024 | 01/23/2025 |
Bid Auth. Approval | 05/01/2025 | |
Construction Approval | 06/01/2025 | |
Project Closeout | 08/31/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 45,100 | 45,100 |
Right of Way | 0 | 0 |
Total Design | 45,100 | 45,100 |
Construction Engineering | 38,900 | 38,900 |
Construction Contract | 310,800 | 310,800 |
Other Construction | 0 | 0 |
Total Construction | 349,700 | 349,700 |
Total TIB Funding | 394,800 | 394,800 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
HARRINGTON | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Replace the ADA ramps as indicated on the vicinity map.
Existing Condition
Project Benefits
- SE portion of the city will have increased pedestrian accessability.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |