Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of George's W Montmorency Multiuse Path

P-E-858(P02)-1

P-E-858(P02)-1
W Montmorency Multiuse Path

Washington Way S to Windsor Ave

FY 2026 Active Transportation Program
Current Phase : Design
Total TIB Funding : $250,000

County: Grant   |   Legislative District: 13   |   Project Length: 1,000.00   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date:

Project Information

Lead Agency GEORGE
Funding Year 2026
Program ATP
Current Phase Design
Legislative District 13
Congressional District 4
Federal Route Number 9999
Project Length 1000.00 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Pedestrian
Project Contact Aaron Harwood
Contact Email pwd@cityofgeorge.org
TIB Engineer Jonathan Heusman
Last Payment Date
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date   02/27/2025
Predesign Approval
Design Approval 01/01/2025 01/27/2025
Bid Auth. Approval 04/30/2025
Construction Approval 06/30/2025
Project Closeout 12/31/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 28,550 28,550
Right of Way 0 0
Total Design 28,550 28,550
     
Construction Engineering 28,550 28,550
Construction Contract 192,900 192,900
Other Construction 0 0
Total Construction 221,450 221,450
     
Total TIB Funding 250,000 250,000

Local Funding Partners

Funding Amount Percent
GEORGE 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

The proposed project will fill a gap in pedestrian facilities between existing sidewalk and frontage improvements (pathway) constructed by a developer.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments