Currently, there are no sidewalks on the east side of George Washington Way between Comstock Street and Bradley Boulevard.
Projects — TIB Project Information
TIB Project Information
City of Richland's George Washington Way Sidewalk
P-E-171(P07)-1
P-E-171(P07)-1
George Washington Way Sidewalk
Comstock St to Bradley Blvd
FY 2026 Active Transportation Program
Current Phase : Design
Total TIB Funding : $850,000
County: Benton | Legislative District: 8 | Project Length: 1,411.00 | TIB Engineer: Jonathan Heusman | Last Payment Date:
Project Information
Lead Agency | RICHLAND |
Funding Year | 2026 |
Program | ATP |
Current Phase | Design |
Legislative District | 8 |
Congressional District | 4 |
Federal Route Number | 3475 |
Project Length | 1411.00 mi. |
ADT | 40,616 |
Functional Class | Principal |
Type of Work | Pedestrian |
Project Contact | Carlo DAlessandro |
Contact Email | Cdalessandro@ci.richland.wa.us |
TIB Engineer | Jonathan Heusman |
Last Payment Date | |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 08/04/2025 | 03/28/2025 |
Bid Auth. Approval | 03/02/2026 | |
Construction Approval | 04/21/2026 | |
Project Closeout | 10/31/2026 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 113,333 | 141,666 |
Right of Way | 0 | 0 |
Total Design | 113,333 | 141,666 |
Construction Engineering | 28,334 | 35,418 |
Construction Contract | 708,333 | 885,416 |
Other Construction | 0 | 0 |
Total Construction | 736,667 | 920,834 |
Total TIB Funding | 850,000 | 1,062,500 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
RICHLAND | 212,500 | 100.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 212,500 | 0.0% |
Project Description
The proposed project installs an 8-foot-wide sidewalk that will integrate with ADA facilities at Comstock Street and Bradley Boulevard.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Supports economic development;
- Completes gap
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |