City of Spokane's Driscoll Blvd Sidewalks

P-E-165(P11)-1

P-E-165(P11)-1
Driscoll Blvd Sidewalks

Garland Ave to Wellesley Ave

FY 2026 Active Transportation Program
Current Phase : Design
Total TIB Funding : $831,500

County: Spokane   |   Legislative District: 3   |   Project Length: 3,260.00   |   TIB Engineer: Andrew Beagle   |   Last Payment Date:

Project Information

Lead Agency SPOKANE
Funding Year 2026
Program ATP
Current Phase Design
Legislative District 3
Congressional District 5
Federal Route Number 3851
Project Length 3260.00 mi.
ADT 8,783
Functional Class Minor
Type of Work Pedestrian
Project Contact Kevin Picanco
Contact Email kpicanco@spokanecity.org
TIB Engineer Andrew Beagle
Last Payment Date
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 01/01/2025 12/17/2024
Bid Auth. Approval 10/15/2025
Construction Approval 12/02/2025
Project Closeout 10/30/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 75,600 151,200
Right of Way 0 0
Total Design 75,600 151,200
     
Construction Engineering 98,600 197,200
Construction Contract 657,300 1,314,600
Other Construction 0 0
Total Construction 755,900 1,511,800
     
Total TIB Funding 831,500 1,663,000

Local Funding Partners

Funding Amount Percent
SPOKANE 831,500 50.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 831,500 50.0%

Project Description

Install separated sidewalks when there is sufficient right of way space to do so. Upgrades to six (6) bus stops for the Spokane Transit Authority (STA) will also be completed as a part of this project for STAs high-performance line 33.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.