 Projects — TIB Project Information

TIB Project Information

City of Mossyrock's City Wide ADA Retrofit

C-W-962(001)-1

C-W-962(001)-1
City Wide ADA Retrofit

City Wide

FY 2026 Complete Streets Program
Current Phase : Design
Total TIB Funding : $491,620

County: Lewis   |   Legislative District: 20   |   Project Length: 0.00   |   TIB Engineer: Chris Langhoff   |   Last Payment Date:

Project Information

Lead Agency MOSSYROCK
Funding Year 2026
Program CSP
Current Phase Design
Legislative District 20
Congressional District 3
Federal Route Number 9999
Project Length 0.00 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Pedestrian
Project Contact Devin Jackson
Contact Email admin@jacksoncivil.com
TIB Engineer Chris Langhoff
Last Payment Date
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2025 12/03/2024
Bid Auth. Approval 04/30/2026
Construction Approval 05/31/2026
Project Closeout 10/31/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 70,200 70,200
Right of Way 0 0
Total Design 70,200 70,200
     
Construction Engineering 35,100 35,100
Construction Contract 386,320 386,320
Other Construction 0 0
Total Construction 421,420 421,420
     
Total TIB Funding 491,620 491,620

Local Funding Partners

Funding Amount Percent
MOSSYROCK 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

This project will replace non-compliant ADA ramps city-wide to ensure equality of access to community businesses and amenities.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments