Working to bring the city into compliance with national ADA standards and ensure that they are serving all demographics inside the community.
Projects — TIB Project Information
TIB Project Information
City of Oakville's City Wide ADA Retrofit
C-W-958(001)-1
C-W-958(001)-1
City Wide ADA Retrofit
Multiple Locations
FY 2026 Complete Streets Program
Current Phase : Design
Total TIB Funding : $372,620
County: Grays Harbor | Legislative District: 19 | Project Length: 0.00 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
Lead Agency | OAKVILLE |
Funding Year | 2026 |
Program | CSP |
Current Phase | Design |
Legislative District | 19 |
Congressional District | 6 |
Federal Route Number | 9999 |
Project Length | 0.00 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Pedestrian |
Project Contact | Devin Jackson |
Contact Email | admin@jacksoncivil.com |
TIB Engineer | Chris Langhoff |
Last Payment Date | |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 03/01/2025 | 02/18/2025 |
Bid Auth. Approval | 04/30/2026 | |
Construction Approval | 05/31/2026 | |
Project Closeout | 10/31/2026 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 53,200 | 53,200 |
Right of Way | 0 | 0 |
Total Design | 53,200 | 53,200 |
Construction Engineering | 26,600 | 26,600 |
Construction Contract | 292,820 | 292,820 |
Other Construction | 0 | 0 |
Total Construction | 319,420 | 319,420 |
Total TIB Funding | 372,620 | 372,620 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
OAKVILLE | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Replacement of non-compliant ADA ramps.
Existing Condition
Project Benefits
- The proposed project updates the transportation infrastructure to better serve pedestrians, ensuring improved multimodal transportation.
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |