City of Montesano's McBryde Sidewalk CSP

C-W-957(001)-1

C-W-957(001)-1
McBryde Sidewalk CSP

Satsop St to Adams St

FY 2026 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $217,761

County: Grays Harbor   |   Legislative District: 24   |   Project Length: 0.00   |   TIB Engineer: Chris Langhoff   |   Last Payment Date:

Project Information

Lead Agency MONTESANO
Funding Year 2026
Program CSP
Current Phase Construction
Legislative District 24
Congressional District 6
Federal Route Number 9999
Project Length 0.00 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Pedestrian
Project Contact Mike Olden
Contact Email molden@montesano.us
TIB Engineer Chris Langhoff
Last Payment Date
Cultural Resource Assessment IDP

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 01/01/2026  
DAHP Assessment Date   04/08/2025
Predesign Approval
Design Approval 12/14/2024 12/18/2024
Bid Auth. Approval 04/22/2025 04/18/2025
Construction Approval 05/15/2025 04/23/2025
Project Closeout 09/15/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 235,000 240,000
Other Construction 0 0
Total Construction 235,000 240,000
     
Funding Surplus - 17,239  
Total TIB Funding 217,761 240,000

Local Funding Partners

Funding Amount Percent
MONTESANO 22,239 9.3%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 22,239 9.3%

Project Description

Continue the work that was completed with TIB funds on the west side of the corridor by installing another 830 feet of sidewalk from Satsop Street to Adams Street.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments