This project will update and install ADA ramps at intersections throughout the city. There are currently 22 ADA ramps that need to be updated or installed to current standards. Approximately half of these ADA ramps have sidewalks but do not have an ADA ramp at all. This project also includes constructing two sections of sidewalks that eliminate gaps for pedestrians.
Projects — TIB Project Information
TIB Project Information
City of Castle Rock's 2025 ADA Improvements
C-W-952(002)-1
C-W-952(002)-1
2025 ADA Improvements
Multiple Locations
FY 2026 Complete Streets Program
Current Phase : Design
Total TIB Funding : $536,170
County: Cowlitz | Legislative District: 19 | Project Length: 0.00 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
Lead Agency | CASTLE ROCK |
Funding Year | 2026 |
Program | CSP |
Current Phase | Design |
Legislative District | 19 |
Congressional District | 3 |
Federal Route Number | 9999 |
Project Length | 0.00 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Pedestrian |
Project Contact | David Vorse |
Contact Email | crpwd@ci.castle-rock.wa.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | 01/16/2025 | |
Predesign Approval | ||
Design Approval | 01/07/2025 | 12/03/2024 |
Bid Auth. Approval | 04/15/2025 | |
Construction Approval | 05/12/2025 | |
Project Closeout | 08/25/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 61,864 | 65,120 |
Right of Way | 0 | 0 |
Total Design | 61,864 | 65,120 |
Construction Engineering | 61,864 | 65,120 |
Construction Contract | 412,442 | 434,150 |
Other Construction | 0 | 0 |
Total Construction | 474,306 | 499,270 |
Total TIB Funding | 536,170 | 564,390 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
CASTLE ROCK | 28,220 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 28,220 | 5.0% |
Project Description
This project is to install 22 ADA ramps and add two new sidewalk sections. The additional sidewalks include 420 of new sidewalks, creating safer access for pedestrians of all ages and abilities.
Existing Condition
Project Benefits
- The city is working on updating ADA ramps to make them more accessible for everyone. This will help people with disabilities easily navigate the city streets and sidewalks. The new ramps and sidewalks will have proper slopes and textures to ensure safety and convenience for all pedestrians. The goal of the city is to create a more inclusive and welcoming environment for all residents and visitors. The improvements to the sidewalks and ADA ramps will benefit the community as a whole.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |