This project will work to bring the city into compliance with national ADA standards and ensure they are serving all demographics within the community.
Projects — TIB Project Information
TIB Project Information
Town of Yacolt's Amboy Curb and ADA Retrofit
C-W-951(001)-1
C-W-951(001)-1
Amboy Curb and ADA Retrofit
Multiple Locations
FY 2026 Complete Streets Program
Current Phase : Design
Total TIB Funding : $288,373
County: Clark | Legislative District: 20 | Project Length: 0.00 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
Lead Agency | YACOLT |
Funding Year | 2026 |
Program | CSP |
Current Phase | Design |
Legislative District | 20 |
Congressional District | 3 |
Federal Route Number | 9999 |
Project Length | 0.00 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Pedestrian |
Project Contact | Devin Jackson |
Contact Email | admin@jacksoncivil.com |
TIB Engineer | Chris Langhoff |
Last Payment Date | |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2025 | 12/16/2024 |
Bid Auth. Approval | 04/30/2026 | |
Construction Approval | 05/31/2026 | |
Project Closeout | 10/31/2026 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 41,135 | 43,300 |
Right of Way | 0 | 0 |
Total Design | 41,135 | 43,300 |
Construction Engineering | 20,520 | 21,600 |
Construction Contract | 226,718 | 238,651 |
Other Construction | 0 | 0 |
Total Construction | 247,238 | 260,251 |
Total TIB Funding | 288,373 | 303,551 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
YACOLT | 15,178 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 15,178 | 5.0% |
Project Description
Replacement of non-compliant ADA ramps and widening of pedestrian facilities.
Existing Condition
Project Benefits
- The proposed project updates the transportation infrastructure to better serve pedestrians and cyclists, ensuring improved multimodal transportation.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |