Madison Avenue is heavily trafficked by cyclists, pedestrians and vehicles. There are multiple schools, preschools, places of worship, businesses, a library, and much more. After school is let out mass amounts of students run across the road, conflicts between vehicles and non-motorized users are present. Not all crossings are ADA compliant, and there are not enough crosswalks along Madison Avenue.
Projects — TIB Project Information
TIB Project Information
City of Bainbridge Island's Madison Ave Nonmotorized Improvements
C-W-830(001)-1
C-W-830(001)-1
Madison Ave Nonmotorized Improvements
SR 305 to Winslow Way
FY 2026 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $500,000
County: Kitsap | Legislative District: 23 | Project Length: 1.36 | TIB Engineer: Chris Langhoff | Last Payment Date: 01/27/2025
Project Information
Lead Agency | BAINBRIDGE ISLAND |
Funding Year | 2026 |
Program | CSP |
Current Phase | Construction |
Legislative District | 23 |
Congressional District | 6 |
Federal Route Number | 6711 |
Project Length | 1.36 mi. |
ADT | 0 |
Functional Class | Minor |
Type of Work | Pedestrian |
Project Contact | Peter Corelis |
Contact Email | pcorelis@bainbridgewa.gov |
TIB Engineer | Chris Langhoff |
Last Payment Date | 01/27/2025 |
Cultural Resource Assessment | Section 106 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 05/17/2024 | |
Delayed Project Date | 05/17/2027 | |
DAHP Assessment Date | 06/27/2024 | |
Predesign Approval | ||
Design Approval | 06/20/2024 | 06/27/2024 |
Bid Auth. Approval | 06/20/2024 | 06/27/2024 |
Construction Approval | 06/20/2024 | 06/27/2024 |
Project Closeout | 05/30/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 61,200 |
Construction Contract | 500,000 | 3,815,481 |
Other Construction | 0 | 0 |
Total Construction | 500,000 | 3,876,681 |
Total TIB Funding | 500,000 | 3,876,681 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
BAINBRIDGE ISLAND | 1,966,681 | 50.7% |
WSDOT Funding | 0 | 0.0% |
STBC | 1,410,000 | 36.4% |
Total Local Funding | 3,376,681 | 87.1% |
Project Description
The following complete street solutions have been incorporated into the Madison Ave design- Lane narrowing for vehicular lanes, sections of dedicated vertically separated bike, sections of buffered bike lanes, portions of widened sidewalk, bus stops.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |