Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Poulsbo's Complete Streets Award

C-W-158(001)-1

C-W-158(001)-1
Complete Streets Award

March 2022 Selection

FY 2023 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $600,000

County: Kitsap   |   Legislative District: 23   |   Project Length: 0.00   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 09/16/2022

Project Information

Lead Agency POULSBO
Funding Year 2023
Program CSP
Current Phase Construction
Legislative District 23
Congressional District 6
Federal Route Number 9999
Project Length 0.00 mi.
ADT 0
Functional Class Collector
Type of Work Pedestrian
Project Contact Diane Lenius
Contact Email dlenius@cityofpoulsbo.com
TIB Engineer Chris Langhoff
Last Payment Date 09/16/2022
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   03/30/2022
Delayed Project Date 03/30/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 07/15/2022 08/18/2022
Bid Auth. Approval 07/15/2022 08/18/2022
Construction Approval 07/15/2022 08/18/2022
Project Closeout 04/30/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 600,000 600,000
Other Construction 0 0
Total Construction 600,000 600,000
     
Total TIB Funding 600,000 600,000

Local Funding Partners

Funding Amount Percent
POULSBO 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Complete Streets Workplan

Item Type of Work Date Added Est. Cost Actual Cost Complete
ADA Curb Ramp Upgrades & Installation Pedestrian Mar 2022 $300,000 $ 0
The City has over 700 curb ramps identified in the ADA Transition Plan that are currently non-compliant and more than 50 locations that are missing curb ramps entirely. This project would upgrade and/or replace up to 50 non-compliant curb ramp locations within the City limits.
Johnson Parkway Pedestrian; Bicycle Feb 2025 $300,000 $ 0
The project will construct approximately 4,400 feet of shared use path and separated sidewalk along with two 11-foot lanes, a roundabout at Johnson Parkway and SR305 intersection, a compact roundabout at Johnson Parkway and Sunrise Ridge Ave, and associated drainage.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments