Accessibility barriers examined were cracked and uneven sidewalks, vertical faults, sidewalk obstructions, and lack of curb ramps. Present curbs and landings had noncompliant width, running slope and cross slope with an Accessibility Index Score of 21-30 or more barriers. Sidewalks had an Accessibility Index Score of 14-20 barriers and overall, ranked a Significant Compliance Issue.
Projects — TIB Project Information
TIB Project Information
City of Port Angeles's Peabody St ADA Improvements
C-W-150(002)-1
C-W-150(002)-1
Peabody St ADA Improvements
Lauridsen St to First St
FY 2026 Complete Streets Program
Current Phase : Design
Total TIB Funding : $590,439
County: Clallam | Legislative District: 24 | Project Length: 0.00 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
Lead Agency | PORT ANGELES |
Funding Year | 2026 |
Program | CSP |
Current Phase | Design |
Legislative District | 24 |
Congressional District | 6 |
Federal Route Number | 7567 |
Project Length | 0.00 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Pedestrian |
Project Contact | Jonathan Boehme |
Contact Email | jboehme@cityofpa.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 01/25/2025 | 01/07/2025 |
Bid Auth. Approval | 12/25/2025 | |
Construction Approval | 01/30/2026 | |
Project Closeout | 08/24/2026 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 28,847 | 57,694 |
Right of Way | 0 | 0 |
Total Design | 28,847 | 57,694 |
Construction Engineering | 30,000 | 60,000 |
Construction Contract | 531,592 | 576,940 |
Other Construction | 0 | 0 |
Total Construction | 561,592 | 636,940 |
Total TIB Funding | 590,439 | 694,634 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
PORT ANGELES | 104,195 | 15.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 104,195 | 15.0% |
Project Description
The project will install approximately thirty-five (35) ADA curb ramps and replace 100 ft of sidewalk.
Existing Condition
Project Benefits
- The City seeks funding from TIB Complete Streets program to provide structural improvements and transition Peabody St. to meet accessibility standards guided by the Port Angeles ADA Transition Plan and Complete Streets ordinance. The aim is to provide accessible pedestrian routes for travelers of all ages and abilities that connect residential areas safely to schools, businesses, transit and paratransit, public library, social services agencies, community center, senior citizen center, and senior living apartments along Peabody St. from Lauridsen St. to First St.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |