Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Gig Harbor's 38th Avenue Improvements Phase 2

C-P-127(001)-1

C-P-127(001)-1
38th Avenue Improvements Phase 2

56th St to Hunt St

FY 2026 Complete Streets Program
Current Phase : Design
Total TIB Funding : $750,000

County: Pierce   |   Legislative District: 26   |   Project Length: 0.51   |   TIB Engineer: Greg Armstrong   |   Last Payment Date:

Project Information

Lead Agency GIG HARBOR
Funding Year 2026
Program CSP
Current Phase Design
Legislative District 26
Congressional District 6
Federal Route Number 3315
Project Length 0.51 mi.
ADT 9,954
Functional Class Minor
Type of Work Pedestrian
Project Contact Stephanie Seibel
Contact Email sseibel@gigharborwa.gov
TIB Engineer Greg Armstrong
Last Payment Date
Cultural Resource Assessment Section 106

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 01/01/2026  
DAHP Assessment Date   09/22/2022
Predesign Approval
Design Approval 02/01/2025 12/03/2024
Bid Auth. Approval 10/01/2025
Construction Approval 10/21/2025
Project Closeout 12/31/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 89,194 530,000
Construction Contract 660,806 3,926,572
Other Construction 0 0
Total Construction 750,000 4,456,572
     
Total TIB Funding 750,000 4,456,572

Local Funding Partners

Funding Amount Percent
GIG HARBOR 3,706,572 83.2%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 3,706,572 83.2%

Project Description

This project will increase safety and connect the 38th Avenue corridor to adjacent PARs by installing sidewalk, bike lane, and roadway lighting. Not only will non-vehicular travelers have increased safety with a new sidewalk (separated in places) and bike lane, but system continuity will be achieved by improving this roadway section to match improvements made in 2022 at the southern end of 38th Avenue. There are two roadway sections due to community input to save significant trees. Segment 2 does not feature a landscaping strip to preserve mature trees. The project will add much needed pedestrian RRFB crosswalks in the corridor.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments