No pedestrian facilities exist on this heavily used segment of roadway from 56th Street to Hunt Street. This segment of sidewalk has been prioritized by the city due to a long-overdue need for pedestrian and bicycle facilities along the 38th Avenue corridor. This particular roadway segment is heavily used by pedestrians, cyclists, and has multiple bus stops for elementary, middle, and high school aged kids. The high pedestrian traffic is proven by a well defined footpath along the shoulder of the unimproved road.This roadway segment has no illumination, which is a danger to vehicles, pedestrians, and cyclists when it is dark.This road segment has no safe pedestrian crossings, which are much needed for pedestrians and school aged children.This project is part of an overall phased approach by the city to have continuous sidewalks from Hunt Street (north city limits on 38th Avenue to south city limits. The city has already completed the southern phase.
Projects — TIB Project Information
TIB Project Information
City of Gig Harbor's 38th Avenue Improvements Phase 2
C-P-127(001)-1
C-P-127(001)-1
38th Avenue Improvements Phase 2
56th St to Hunt St
FY 2026 Complete Streets Program
Current Phase : Design
Total TIB Funding : $750,000
County: Pierce | Legislative District: 26 | Project Length: 0.51 | TIB Engineer: Greg Armstrong | Last Payment Date:
Project Information
Lead Agency | GIG HARBOR |
Funding Year | 2026 |
Program | CSP |
Current Phase | Design |
Legislative District | 26 |
Congressional District | 6 |
Federal Route Number | 3315 |
Project Length | 0.51 mi. |
ADT | 9,954 |
Functional Class | Minor |
Type of Work | Pedestrian |
Project Contact | Stephanie Seibel |
Contact Email | sseibel@gigharborwa.gov |
TIB Engineer | Greg Armstrong |
Last Payment Date | |
Cultural Resource Assessment | Section 106 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 01/01/2026 | |
DAHP Assessment Date | 09/22/2022 | |
Predesign Approval | ||
Design Approval | 02/01/2025 | 12/03/2024 |
Bid Auth. Approval | 10/01/2025 | |
Construction Approval | 10/21/2025 | |
Project Closeout | 12/31/2026 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 89,194 | 530,000 |
Construction Contract | 660,806 | 3,926,572 |
Other Construction | 0 | 0 |
Total Construction | 750,000 | 4,456,572 |
Total TIB Funding | 750,000 | 4,456,572 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
GIG HARBOR | 3,706,572 | 83.2% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 3,706,572 | 83.2% |
Project Description
This project will increase safety and connect the 38th Avenue corridor to adjacent PARs by installing sidewalk, bike lane, and roadway lighting. Not only will non-vehicular travelers have increased safety with a new sidewalk (separated in places) and bike lane, but system continuity will be achieved by improving this roadway section to match improvements made in 2022 at the southern end of 38th Avenue. There are two roadway sections due to community input to save significant trees. Segment 2 does not feature a landscaping strip to preserve mature trees. The project will add much needed pedestrian RRFB crosswalks in the corridor.
Existing Condition
Project Benefits
- The Gig Harbor community has long been awaiting pedestrian and bicycle infrastructure along incomplete corridors. This need is represented by the City Councils support of the 2018 Comprehensive Plan, 2025-2030 TIP, and Climate Action Plan, all of which advocate projects to install complete streets designs. 38th Avenue does not have existing complete streets infrastructure from Hunt to Briarwood Lane. The proposed project will complete a bike lane and sidewalks on the east side of the street, per the citys Complete Streets Ordinance (O-1525). Future capital improvement projects will be connecting the 38th Avenue sidewalk and bike lane from the current terminus at Briarwood Lane to this projects southern limit of 56th Street. This sidewalk and bike lane will serve the residential area of local roads that feed onto 38th Avenue. Additionally, sidewalk and bike lane from Hunt St to 56th St will connect a route for pedestrians and cyclists to travel from the 38th/Hunt St intersection all the way to the Olympic/Point Fosdick intersection, giving them access to a COLI (center of local importance). 38th Avenue is also a bus route for several schools in the area, and connects the city road to the county. With the addition of sidewalk, bike lane, and lighting on 38th Avenue, students can safely ride, roll, or walk to school where it was unsafe to before.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |