The community needs this project to address significant accessibility barriers. Several intersections in the area lack curb ramps, which impedes safe and easy access for individuals using wheelchairs, walkers, or strollers. Additionally, the current driveway crossings have cross slopes that exceed standard maximums, creating hazardous conditions for those using assistive devices. These issues prevent equitable access and pose safety risks. Installing ADA-compliant curb ramps and correcting driveway cross slopes will remove these obstacles, ensuring a safer, more inclusive environment for all residents, particularly those with mobility impairments.
Projects — TIB Project Information
TIB Project Information
Snohomish County's 204th Street SW ADA Upgrades
C-P-031(002)-1
C-P-031(002)-1
204th Street SW ADA Upgrades
Various Locations
FY 2026 Complete Streets Program
Current Phase : Bid Authorization
Total TIB Funding : $408,106
County: Snohomish | Legislative District: 32 | Project Length: 0.00 | TIB Engineer: Greg Armstrong | Last Payment Date: 04/04/2025
Project Information
Lead Agency | SNOHOMISH COUNTY |
Funding Year | 2026 |
Program | CSP |
Current Phase | Bid Authorization |
Legislative District | 32 |
Congressional District | 1, 2 |
Federal Route Number | 9999 |
Project Length | 0.00 mi. |
ADT | 0 |
Functional Class | Local Access |
Type of Work | Pedestrian |
Project Contact | Megan Olsen |
Contact Email | megan.olsen@snoco.org |
TIB Engineer | Greg Armstrong |
Last Payment Date | 04/04/2025 |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | 02/27/2025 | |
Predesign Approval | ||
Design Approval | 02/01/2025 | 12/18/2024 |
Bid Auth. Approval | 04/10/2025 | 04/10/2025 |
Construction Approval | 05/01/2025 | |
Project Closeout | 06/20/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 84,573 | 118,000 |
Right of Way | 0 | 0 |
Total Design | 84,573 | 118,000 |
Construction Engineering | 42,286 | 59,000 |
Construction Contract | 281,247 | 392,410 |
Other Construction | 0 | 0 |
Total Construction | 323,533 | 451,410 |
Total TIB Funding | 408,106 | 569,410 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SNOHOMISH COUNTY | 161,304 | 28.3% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 161,304 | 28.3% |
Project Description
Install ADA-compliant curb ramps where absent and upgrade driveway crossings to meet standard slopes, enhancing accessibility and safety for all pedestrians.
Existing Condition
Project Benefits
- This project focuses on enhancing accessibility and safety at multiple intersections and driveway crossings. The key elements include installing ADA-compliant curb ramps where none currently exist and reconstructing driveway crossings to meet standard cross slope requirements. This project incorporates the following Complete Streets Elements: Accessibility: Installing ADA-compliant curb ramps meets the needs of individuals with disabilities, ensuring that all users can navigate the area safely. Safety: Correcting excessive cross slopes at driveway crossings reduces hazards and enhances safety for pedestrians. Inclusivity: The project promotes inclusivity by ensuring curb ramps and driveway crossings accommodate all community members, regardless of physical ability, fostering a more equitable transportation network. Connectivity: Upgrading curb ramps and driveway crossings improves the connectivity of the street network, allowing for smoother and more efficient pedestrian movement and better integration with existing infrastructure.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |