TIB Project Information

Snohomish County's 204th Street SW ADA Upgrades

C-P-031(002)-1

C-P-031(002)-1
204th Street SW ADA Upgrades

Various Locations

FY 2026 Complete Streets Program
Current Phase : Bid Authorization
Total TIB Funding : $408,106

County: Snohomish   |   Legislative District: 32   |   Project Length: 0.00   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 04/04/2025

Project Information

Lead Agency SNOHOMISH COUNTY
Funding Year 2026
Program CSP
Current Phase Bid Authorization
Legislative District 32
Congressional District 1, 2
Federal Route Number 9999
Project Length 0.00 mi.
ADT 0
Functional Class Local Access
Type of Work Pedestrian
Project Contact Megan Olsen
Contact Email megan.olsen@snoco.org
TIB Engineer Greg Armstrong
Last Payment Date 04/04/2025
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date   02/27/2025
Predesign Approval
Design Approval 02/01/2025 12/18/2024
Bid Auth. Approval 04/10/2025 04/10/2025
Construction Approval 05/01/2025
Project Closeout 06/20/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 84,573 118,000
Right of Way 0 0
Total Design 84,573 118,000
     
Construction Engineering 42,286 59,000
Construction Contract 281,247 392,410
Other Construction 0 0
Total Construction 323,533 451,410
     
Total TIB Funding 408,106 569,410

Local Funding Partners

Funding Amount Percent
SNOHOMISH COUNTY 161,304 28.3%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 161,304 28.3%

Project Description

Install ADA-compliant curb ramps where absent and upgrade driveway crossings to meet standard slopes, enhancing accessibility and safety for all pedestrians.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments