Insufficient pedestrian amenities deter foot traffic and limit opportunities for economic growth and revitalization.
Projects — TIB Project Information
TIB Project Information
City of Zillah's 1st Avenue Pedestrian Improvements
C-E-947(003)-1
C-E-947(003)-1
1st Avenue Pedestrian Improvements
1st Ave Bulbouts
FY 2026 Complete Streets Program
Current Phase : Design
Total TIB Funding : $700,000
County: Yakima | Legislative District: 15 | Project Length: 0.00 | TIB Engineer: Jonathan Heusman | Last Payment Date: 04/10/2025
Project Information
Lead Agency | ZILLAH |
Funding Year | 2026 |
Program | CSP |
Current Phase | Design |
Legislative District | 15 |
Congressional District | 4 |
Federal Route Number | 6445 |
Project Length | 0.00 mi. |
ADT | 0 |
Functional Class | |
Type of Work | |
Project Contact | Ardele Steele |
Contact Email | ASteele@cityofzillah.us |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 04/10/2025 |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 01/01/2025 | 02/04/2025 |
Bid Auth. Approval | 05/16/2025 | |
Construction Approval | 06/13/2025 | |
Project Closeout | 09/05/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 80,769 | 89,743 |
Right of Way | 0 | 0 |
Total Design | 80,769 | 89,743 |
Construction Engineering | 80,769 | 89,743 |
Construction Contract | 538,462 | 598,291 |
Other Construction | 0 | 0 |
Total Construction | 619,231 | 688,034 |
Total TIB Funding | 700,000 | 777,777 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
ZILLAH | 77,777 | 10.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 77,777 | 10.0% |
Project Description
The project consists of the construction of pedestrian bulb-outs for safety and better pedestrian access along First Avenue.
Existing Condition
Project Benefits
- The project consists of the construction of Pedestrian bulb-outs for safety along First Avenue as well as downtown streetscape improvements.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |