City of Zillah's 1st Avenue Pedestrian Improvements

C-E-947(003)-1

C-E-947(003)-1
1st Avenue Pedestrian Improvements

1st Ave Bulbouts

FY 2026 Complete Streets Program
Current Phase : Design
Total TIB Funding : $700,000

County: Yakima   |   Legislative District: 15   |   Project Length: 0.00   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 04/10/2025

Project Information

Lead Agency ZILLAH
Funding Year 2026
Program CSP
Current Phase Design
Legislative District 15
Congressional District 4
Federal Route Number 6445
Project Length 0.00 mi.
ADT 0
Functional Class
Type of Work
Project Contact Ardele Steele
Contact Email ASteele@cityofzillah.us
TIB Engineer Jonathan Heusman
Last Payment Date 04/10/2025
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 01/01/2025 02/04/2025
Bid Auth. Approval 05/16/2025
Construction Approval 06/13/2025
Project Closeout 09/05/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 80,769 89,743
Right of Way 0 0
Total Design 80,769 89,743
     
Construction Engineering 80,769 89,743
Construction Contract 538,462 598,291
Other Construction 0 0
Total Construction 619,231 688,034
     
Total TIB Funding 700,000 777,777

Local Funding Partners

Funding Amount Percent
ZILLAH 77,777 10.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 77,777 10.0%

Project Description

The project consists of the construction of pedestrian bulb-outs for safety and better pedestrian access along First Avenue.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments