W. Fir Street has been identified as a location with high pedestrian activity within the City of Connell that lacks pedestrian facilities yet contains nearly 200 homes and connects multiple public and private pedestrian generators.
Projects — TIB Project Information
TIB Project Information
City of Connell's W Fir Street Sidewalk Improvements
C-E-926(002)-1
C-E-926(002)-1
W Fir Street Sidewalk Improvements
SR 260 to Columbia Ave
FY 2026 Complete Streets Program
Current Phase : Design
Total TIB Funding : $492,030
County: Franklin | Legislative District: 9 | Project Length: 0.42 | TIB Engineer: Jonathan Heusman | Last Payment Date:
Project Information
Lead Agency | CONNELL |
Funding Year | 2026 |
Program | CSP |
Current Phase | Design |
Legislative District | 9 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.42 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Pedestrian |
Project Contact | Hallie Tuck |
Contact Email | htuck@connellwa.org |
TIB Engineer | Jonathan Heusman |
Last Payment Date | |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 01/01/2025 | 03/06/2025 |
Bid Auth. Approval | 12/01/2025 | |
Construction Approval | 02/01/2026 | |
Project Closeout | 10/01/2026 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 54,000 | 60,000 |
Right of Way | 0 | 0 |
Total Design | 54,000 | 60,000 |
Construction Engineering | 45,000 | 50,000 |
Construction Contract | 393,030 | 436,700 |
Other Construction | 0 | 0 |
Total Construction | 438,030 | 486,700 |
Total TIB Funding | 492,030 | 546,700 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
CONNELL | 54,670 | 10.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 54,670 | 10.0% |
Project Description
Install a cement concrete sidewalk, traffic curb and gutter as needed for ADA compliance, sidewalk ramps, and crosswalk lines along W. Fir Street.
Existing Condition
Project Benefits
- The W. Fir Street Sidewalk Improvements Project will provide pedestrian accessibility to a quadrant of Connell that currently lacks pedestrian facilities. At present, no such facilities exist in an area housing a large portion of Connells population, and the area provides direct access to one of the Citys three parks. This project will promote pedestrian access for the residents adjacent to the project area and provide citywide access to Striker Park.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |