Town of Oakesdale's ADA Ramp Replacement

C-E-915(001)-1

C-E-915(001)-1
ADA Ramp Replacement

Entire Town

FY 2026 Complete Streets Program
Current Phase : Design
Total TIB Funding : $400,000

County: Whitman   |   Legislative District: 9   |   Project Length: 0.00   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date:

Project Information

Lead Agency OAKESDALE
Funding Year 2026
Program CSP
Current Phase Design
Legislative District 9
Congressional District 5
Federal Route Number 9999
Project Length 0.00 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Pedestrian
Project Contact Mary DeGon
Contact Email townofoakesdale@msn.com
TIB Engineer Jonathan Heusman
Last Payment Date
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2025 12/10/2024
Bid Auth. Approval 03/01/2026
Construction Approval 05/01/2026
Project Closeout 10/01/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 53,846 53,846
Right of Way 0 0
Total Design 53,846 53,846
     
Construction Engineering 38,462 38,462
Construction Contract 307,692 307,692
Other Construction 0 0
Total Construction 346,154 346,154
     
Total TIB Funding 400,000 400,000

Local Funding Partners

Funding Amount Percent
OAKESDALE 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Construct/replace 30 ADA ramps to current standards.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.