 Projects — TIB Project Information

TIB Project Information

City of Kettle Falls's High School Sidewalk Corridor

C-E-903(001)-1

C-E-903(001)-1
High School Sidewalk Corridor

High School Enterance to approximately 400' E of Juniper

FY 2026 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $173,491

County: Stevens   |   Legislative District: 7   |   Project Length: 400.00   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 02/11/2025

Project Information

Lead Agency KETTLE FALLS
Funding Year 2026
Program CSP
Current Phase Construction
Legislative District 7
Congressional District 5
Federal Route Number 33GB
Project Length 400.00 mi.
ADT 0
Functional Class Collector
Type of Work Pedestrian
Project Contact Dave Willey
Contact Email dwilley@kettle-falls.com
TIB Engineer Andrew Beagle
Last Payment Date 02/11/2025
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   05/17/2024
Delayed Project Date 05/17/2027  
DAHP Assessment Date   07/02/2024
Predesign Approval
Design Approval 06/24/2024 06/17/2024
Bid Auth. Approval 07/01/2024 07/24/2024
Construction Approval 12/15/2024 01/13/2025
Project Closeout 04/30/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 17,000 30,290
Right of Way 0 0
Total Design 17,000 30,290
     
Construction Engineering 15,000 36,683
Construction Contract 149,000 218,665
Other Construction 0 0
Total Construction 164,000 255,348
     
Funding Surplus - 7,509  
Total TIB Funding 173,491 285,638

Local Funding Partners

Funding Amount Percent
KETTLE FALLS 0 0.0%
WSDOT Funding 0 0.0%
NEWRTPO  112,147 39.3%
 
 
 
 
 
 
 
Total Local Funding 112,147 39.3%

Project Description

Construct sidewalk.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments