The immediate need for the community is to replace non-ADA compliant ramps and install crosswalks where none exist or are non-compliant. The priority non-compliant ADA ramps are on walking routes to schools or within the downtown corridors where walkability and connectivity is important.
Projects — TIB Project Information
TIB Project Information
City of Sunnyside's ADA Ramp Replacement
C-E-179(002)-1
C-E-179(002)-1
ADA Ramp Replacement
Multiple Locations
FY 2026 Complete Streets Program
Current Phase : Bid Authorization
Total TIB Funding : $437,138
County: Yakima | Legislative District: 15 | Project Length: 0.00 | TIB Engineer: Jonathan Heusman | Last Payment Date: 03/13/2025
Project Information
Lead Agency | SUNNYSIDE |
Funding Year | 2026 |
Program | CSP |
Current Phase | Bid Authorization |
Legislative District | 15 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.00 mi. |
ADT | 0 |
Functional Class | Local Access |
Type of Work | Pedestrian |
Project Contact | Raul Sanchez |
Contact Email | rsanchez@sunnyside-wa.gov |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 03/13/2025 |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | 01/23/2025 | |
Predesign Approval | ||
Design Approval | 01/06/2025 | 01/14/2025 |
Bid Auth. Approval | 06/02/2025 | 04/18/2025 |
Construction Approval | 06/23/2025 | |
Project Closeout | 08/22/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 47,073 | 55,380 |
Right of Way | 0 | 0 |
Total Design | 47,073 | 55,380 |
Construction Engineering | 53,805 | 63,300 |
Construction Contract | 336,260 | 395,600 |
Other Construction | 0 | 0 |
Total Construction | 390,065 | 458,900 |
Total TIB Funding | 437,138 | 514,280 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SUNNYSIDE | 77,142 | 15.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 77,142 | 15.0% |
Project Description
The project will replace 26 non-compliant ADA ramps and will replace 13 non-compliant crosswalk markings and/or add crosswalk markings where none exist.
Existing Condition
Project Benefits
- The proposed project identifies 26 curb ramps in 6 different intersections that are non-ADA compliant to be replaced and made ADA compliant. The selected locations are in the vicinity of five different schools, where safe pedestrian access is extremely important. The completion of this project would promote a safer city and more accessible routes.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |