City of Kennewick's Pedestrian Safety Improvements

C-E-173(003)-1

C-E-173(003)-1
Pedestrian Safety Improvements

Multiple Locations

FY 2026 Complete Streets Program
Current Phase : Closeout
Total TIB Funding : $192,456

County: Benton   |   Legislative District: 8   |   Project Length: 0.01   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 03/27/2025

Project Information

Lead Agency KENNEWICK
Funding Year 2026
Program CSP
Current Phase Closeout
Legislative District 8
Congressional District 4
Federal Route Number 3406
Project Length 0.01 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Pedestrian
Project Contact Heath Mellotte
Contact Email heath.mellotte@ci.kennewick.wa.us
TIB Engineer Jonathan Heusman
Last Payment Date 03/27/2025
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   05/17/2024
Delayed Project Date 05/17/2027  
DAHP Assessment Date   06/14/2024
Predesign Approval
Design Approval 05/31/2024 06/20/2024
Bid Auth. Approval 07/14/2024 07/16/2024
Construction Approval 08/19/2024 08/09/2024
Project Closeout 01/31/2025 04/08/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 17,600 8,250
Construction Contract 190,720 232,320
Other Construction 0 0
Total Construction 208,320 240,570
     
Funding Surplus - 15,864  
Total TIB Funding 192,456 240,570

Local Funding Partners

Funding Amount Percent
KENNEWICK 48,114 20.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 48,114 20.0%

Project Description

Install new ADA ramps and Rectangular Rapid Flashing Beacons (RRFBs) at W. Clearwater Ave/N Johnson St and S. Olympia St/W 36th Ave intersections where no crossings currently exist.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments