Many of the older elementary and middle schools in Spokane lack the accessible pedestrian facilities that are present at the recently built schools. Marked school crosswalks and other walk routes are missing ADA ramps. In other locations the sidewalk stops and starts along the walk route. Some existing school crosswalks experience higher speed traffic and streets that are wider than needed. Parents often walk kids to and from school with younger siblings in a stroller or on a bike. The lack of ADA ramps provides a barrier and safety concern for anyone using wheels.
Projects — TIB Project Information
TIB Project Information
City of Spokane's Spokane School Walk Routes
C-E-165(005)-1
C-E-165(005)-1
Spokane School Walk Routes
Various
FY 2026 Complete Streets Program
Current Phase : Design
Total TIB Funding : $1,636,595
County: Spokane | Legislative District: 3 | Project Length: 0.00 | TIB Engineer: Andrew Beagle | Last Payment Date:
Project Information
Lead Agency | SPOKANE |
Funding Year | 2026 |
Program | CSP |
Current Phase | Design |
Legislative District | 3, 6 |
Congressional District | 5 |
Federal Route Number | |
Project Length | 0.00 mi. |
ADT | 0 |
Functional Class | Local Access |
Type of Work | Pedestrian |
Project Contact | Kevin Picanco |
Contact Email | kpicanco@spokanecity.org |
TIB Engineer | Andrew Beagle |
Last Payment Date | |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2025 | 12/17/2024 |
Bid Auth. Approval | 10/15/2025 | |
Construction Approval | 12/02/2025 | |
Project Closeout | 10/30/2026 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 148,563 | 185,704 |
Right of Way | 0 | 0 |
Total Design | 148,563 | 185,704 |
Construction Engineering | 193,778 | 242,223 |
Construction Contract | 1,294,254 | 1,617,817 |
Other Construction | 0 | 0 |
Total Construction | 1,488,032 | 1,860,040 |
Total TIB Funding | 1,636,595 | 2,045,744 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SPOKANE | 409,149 | 20.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 409,149 | 20.0% |
Project Description
The project includes school-related ADA ramp installation, sidewalk infill, upgraded crosswalk markings, bumpouts at select locations, and one RRFB at an arterial crosswalk.
Existing Condition
Project Benefits
- This project with improve walk routes to Audubon Elementary, Browne Elementary, Garfield Elementary, Indian Trail Elementary, Logan Elementary and Yasuhara Middle School.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |