Olympia Way and Nichols Blvd. front Northlake Elementary school and Lake Sacajawea and see a lot of foot traffic to and from the school. Pavement condition is poor, ADA ramps need to be replaced and brought up to standards signal needs to be replaced with appropriate pedestrian upgrades.
Projects — TIB Project Information
TIB Project Information
City of Longview's Olympia Way and Nichols Blvd
8-5-187(018)-1
8-5-187(018)-1
Olympia Way and Nichols Blvd
Multiple Locations
FY 2025 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $1,747,877
County: Cowlitz | Legislative District: 19 | Project Length: 0.50 | TIB Engineer: Chris Langhoff | Last Payment Date: 02/13/2025
Project Information
Lead Agency | LONGVIEW |
Funding Year | 2025 |
Program | UAP |
Current Phase | Construction |
Legislative District | 19 |
Congressional District | 3 |
Federal Route Number | 6828 |
Project Length | 0.50 mi. |
ADT | 5,200 |
Functional Class | Minor |
Type of Work | Resurfacing |
Project Contact | Morgan Palmer |
Contact Email | morgan.palmer@ci.longview.wa.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | 02/13/2025 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2028 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 01/01/2024 | 12/20/2023 |
Bid Auth. Approval | 05/01/2024 | 04/18/2024 |
Construction Approval | 05/15/2024 | 05/17/2024 |
Project Closeout | 06/30/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 340,800 | 320,000 |
Right of Way | 0 | 0 |
Total Design | 340,800 | 320,000 |
Construction Engineering | 206,400 | 327,000 |
Construction Contract | 2,059,200 | 1,705,651 |
Other Construction | 0 | 0 |
Total Construction | 2,265,600 | 2,032,651 |
Funding Surplus | - 858,523 | |
Total TIB Funding | 1,747,877 | 2,352,651 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
LONGVIEW | 604,774 | 25.7% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 604,774 | 25.7% |
Project Description
Grind and inlay with HMA after replacing broken concrete panels to restore pavement condition, replace ADA ramps, replace and/or upgrade signal system and add bike lanes.
Existing Condition
Project Benefits
- Improves arterial network;
- Restores structural condition;
- Builds multimodal facilities
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |