City of Longview's Olympia Way and Nichols Blvd

8-5-187(018)-1

8-5-187(018)-1
Olympia Way and Nichols Blvd

Multiple Locations

FY 2025 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $1,747,877

County: Cowlitz   |   Legislative District: 19   |   Project Length: 0.50   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 02/13/2025

Project Information

Lead Agency LONGVIEW
Funding Year 2025
Program UAP
Current Phase Construction
Legislative District 19
Congressional District 3
Federal Route Number 6828
Project Length 0.50 mi.
ADT 5,200
Functional Class Minor
Type of Work Resurfacing
Project Contact Morgan Palmer
Contact Email morgan.palmer@ci.longview.wa.us
TIB Engineer Chris Langhoff
Last Payment Date 02/13/2025
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2028  
DAHP Assessment Date  
Predesign Approval
Design Approval 01/01/2024 12/20/2023
Bid Auth. Approval 05/01/2024 04/18/2024
Construction Approval 05/15/2024 05/17/2024
Project Closeout 06/30/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 340,800 320,000
Right of Way 0 0
Total Design 340,800 320,000
     
Construction Engineering 206,400 327,000
Construction Contract 2,059,200 1,705,651
Other Construction 0 0
Total Construction 2,265,600 2,032,651
     
Funding Surplus - 858,523  
Total TIB Funding 1,747,877 2,352,651

Local Funding Partners

Funding Amount Percent
LONGVIEW 604,774 25.7%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 604,774 25.7%

Project Description

Grind and inlay with HMA after replacing broken concrete panels to restore pavement condition, replace ADA ramps, replace and/or upgrade signal system and add bike lanes.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments