Clark County's NE 179th St and NE 29th Ave Intersection Improvement

8-5-006(045)-1

8-5-006(045)-1
NE 179th St and NE 29th Ave Intersection Improvement

NE 29th Ave Intersection

FY 2026 Urban Arterial Program
Current Phase : Design
Total TIB Funding : $3,000,000

County: Clark   |   Legislative District: 18   |   Project Length: 0.68   |   TIB Engineer: Chris Langhoff   |   Last Payment Date:

Project Information

Lead Agency CLARK COUNTY
Funding Year 2026
Program UAP
Current Phase Design
Legislative District 18
Congressional District 3
Federal Route Number 4247
Project Length 0.68 mi.
ADT 8,749
Functional Class Principal
Type of Work Safety
Project Contact John Mcsherry
Contact Email john.mcsherry@clark.wa.gov
TIB Engineer Chris Langhoff
Last Payment Date
Cultural Resource Assessment Section 106

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 01/01/2026  
DAHP Assessment Date  
Predesign Approval
Design Approval 03/01/2025 02/05/2025
Bid Auth. Approval 04/30/2025
Construction Approval 05/30/2025
Project Closeout 12/31/2027
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 157,386 967,538
Construction Contract 2,819,469 17,332,803
Other Construction 23,145 142,285
Total Construction 3,000,000 18,442,626
     
Total TIB Funding 3,000,000 18,442,626

Local Funding Partners

Funding Amount Percent
CLARK COUNTY 13,942,626 75.6%
WSDOT Funding 0 0.0%
STBG UL  1,500,000 9.7%
 
 
 
 
 
 
 
Total Local Funding 15,442,626 85.3%

Project Description

This Project will construct a dual lane roundabout adding ADA compliant pedestrian and bicycle facilities through the intersection. The project will improve intersection visibility by installing roadway lighting, and markings including signing, targeted lighting, reflective candle sticks, and RRFBs at pedestrian cross walks.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.