City of Yakima's S 72nd Avenue Roundabout

8-4-180(029)-1

8-4-180(029)-1
S 72nd Avenue Roundabout

W Washington Ave Intersection

FY 2026 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $1,045,166

County: Yakima   |   Legislative District: 14   |   Project Length: 0.05   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date:

Project Information

Lead Agency YAKIMA
Funding Year 2026
Program UAP
Current Phase Construction
Legislative District 14
Congressional District 4
Federal Route Number 4711
Project Length 0.05 mi.
ADT 10,127
Functional Class Minor
Type of Work Traffic Control
Project Contact Bill Preston
Contact Email bill.preston@yakimawa.gov
TIB Engineer Jonathan Heusman
Last Payment Date
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 01/01/2026  
DAHP Assessment Date   06/03/2021
Predesign Approval
Design Approval 01/01/2025 02/11/2025
Bid Auth. Approval 03/05/2025 02/28/2025
Construction Approval 04/28/2025 04/22/2025
Project Closeout 12/31/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 220,200 427,000
Construction Contract 1,279,800 1,476,619
Other Construction 0 0
Total Construction 1,500,000 1,903,619
     
Funding Surplus - 454,834  
Total TIB Funding 1,045,166 1,903,619

Local Funding Partners

Funding Amount Percent
YAKIMA 58,453 3.1%
WSDOT Funding 0 0.0%
WA St. Legislature  800,000 32.0%
 
 
 
 
 
 
 
Total Local Funding 858,453 35.1%

Project Description

The project will reconstruct the W. Washington Avenue and S. 72nd Avenue intersection into a single lane roundabout with 20 foot lanes including sidewalk, curb and gutter. A 19-foot truck apron will be constructed to accommodate larger vehicles as this is a freight route with a large presence of agricultural trucks during harvest.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.