TIB Project Information

City of Walla Walla's Myra Road South Extension

8-4-176(029)-1

8-4-176(029)-1
Myra Road South Extension

SR 125 to Taumarson Rd

FY 2026 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $1,981,760

County: Walla Walla   |   Legislative District: 16   |   Project Length: 0.52   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date:

Project Information

Lead Agency WALLA WALLA
Funding Year 2026
Program UAP
Current Phase Construction
Legislative District 16
Congressional District 5
Federal Route Number 7161
Project Length 0.52 mi.
ADT 10,400
Functional Class Minor
Type of Work New Location
Project Contact Mike Laughery
Contact Email mlaughery@wallawallawa.gov
TIB Engineer Jonathan Heusman
Last Payment Date
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 01/01/2026  
DAHP Assessment Date   06/05/2024
Predesign Approval
Design Approval 12/31/2024 12/12/2024
Bid Auth. Approval 01/16/2025 01/16/2025
Construction Approval 03/12/2025 02/27/2025
Project Closeout 07/31/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 267,857 1,481,435
Construction Contract 2,232,143 7,966,896
Other Construction 0 100,000
Total Construction 2,500,000 9,548,331
     
Funding Surplus - 518,240  
Total TIB Funding 1,981,760 9,548,331

Local Funding Partners

Funding Amount Percent
WALLA WALLA 0 0.0%
WSDOT Funding 0 0.0%
Tax Increment Area Financing  7,566,571 79.2%
 
 
 
 
 
 
 
Total Local Funding 7,566,571 79.2%

Project Description

The Myra Road South Extension Project (Project) proposes to extend Myra Road from its present terminus at SR-125 south to Taumarson Road linking the south Walla Walla area with US-12 and providing direct access to over 50 acres of commercial and residential zoned vacant land south of SR-125.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments