Airway Heights is advancing a downtown revitalization corridor plan to promote transit, active transportation, and reliable mobility as key elements of a renewed identity for an FHWA-designated, historically disadvantaged community (HDC). There is a need to calm traffic, establish safe ped/bike crossings, improve access to City and Kalispel Tribe developments, and promote stable travel movements.
Projects — TIB Project Information
TIB Project Information
City of Airway Heights's Garfield U.S. 2 Roundabout
8-3-893(008)-1
8-3-893(008)-1
Garfield U.S. 2 Roundabout
Garfield Rd Intersection
FY 2026 Urban Arterial Program
Current Phase : Design
Total TIB Funding : $2,018,552
County: Spokane | Legislative District: 6 | Project Length: 0.15 | TIB Engineer: Andrew Beagle | Last Payment Date:
Project Information
Lead Agency | AIRWAY HEIGHTS |
Funding Year | 2026 |
Program | UAP |
Current Phase | Design |
Legislative District | 6 |
Congressional District | 5 |
Federal Route Number | 0002 |
Project Length | 0.15 mi. |
ADT | 34,000 |
Functional Class | Principal |
Type of Work | Safety |
Project Contact | Heather Trautman AICP CCEO |
Contact Email | htrautman@cawh.org |
TIB Engineer | Andrew Beagle |
Last Payment Date | |
Cultural Resource Assessment | Section 106 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2029 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2025 | 03/28/2025 |
Bid Auth. Approval | 12/02/2025 | |
Construction Approval | 02/17/2026 | |
Project Closeout | 10/31/2026 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 51,452 | 99,129 |
Right of Way | 124,569 | 240,000 |
Total Design | 176,021 | 339,129 |
Construction Engineering | 192,943 | 371,734 |
Construction Contract | 1,649,588 | 3,178,176 |
Other Construction | 0 | 0 |
Total Construction | 1,842,531 | 3,549,910 |
Total TIB Funding | 2,018,552 | 3,889,039 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
AIRWAY HEIGHTS | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
FFY 2024 Congressionally Directed Spending | 1,870,487 | 48.1% |
Total Local Funding | 1,870,487 | 48.1% |
Project Description
The roundabout would be the fifth of eight planned on U.S. 2 (2 constructed, 2 complete by 2025).
Existing Condition
Project Benefits
- This would promote safety and reliable multimodal access 20 current businesses and 19 commercial parcels primed for development within 1/4-mile, LOS will be improved.
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |