5th Street NE as a vital east-west connection for residents. Link Transit Routes and three schools are directly accessed from 5th Street NE. An additional school, two parks and the commercial business district are all within a three block radius of this corridor. The City has recently built 4650 lf of urban and SRTS funded improvements on 5th St. This has left an 850ft and a 1300ft gap in an otherwise continuous multimodal corridor, including the Eastmont Ave intersection performing at LOS F and with a higher rate of crashes than other comparable intersections.
Projects — TIB Project Information
TIB Project Information
City of East Wenatchee's 5th Street NE Safety and Multimodal Improvements
8-3-161(016)-1
8-3-161(016)-1
5th Street NE Safety and Multimodal Improvements
N Baker Ave to N Kentucky Ave
FY 2025 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $1,469,280
County: Douglas | Legislative District: 12 | Project Length: 1.30 | TIB Engineer: Andrew Beagle | Last Payment Date: 04/29/2026
Project Information
| Lead Agency | EAST WENATCHEE |
| Funding Year | 2025 |
| Program | UAP |
| Current Phase | Construction |
| Legislative District | 12, 7 |
| Congressional District | 4 |
| Federal Route Number | 5906 |
| Project Length | 1.30 mi. |
| ADT | 2,500 |
| Functional Class | Collector |
| Type of Work | Safety |
| Project Contact | Garren Melton |
| Contact Email | gmelton@eastwenatcheewa.gov |
| TIB Engineer | Andrew Beagle |
| Last Payment Date | 04/29/2026 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/01/2023 | |
| Delayed Project Date | 07/01/2028 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/01/2024 | 01/11/2024 |
| Bid Auth. Approval | 12/01/2025 | 10/29/2025 |
| Construction Approval | 01/20/2026 | 01/23/2026 |
| Project Closeout | 11/01/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 384,615 | 729,350 |
| Right of Way | 0 | 0 |
| Total Design | 384,615 | 729,350 |
| Construction Engineering | 192,308 | 634,261 |
| Construction Contract | 1,923,077 | 3,582,850 |
| Other Construction | 0 | 103,975 |
| Total Construction | 2,115,385 | 4,321,086 |
| Funding Surplus | - 1,030,720 | |
| Total TIB Funding | 1,469,280 | 5,050,436 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| EAST WENATCHEE | 0 | 0.0% |
| WSDOT Funding | 3,297,402 | 65.3% |
| East Wenatchee Water District | 283,754 | 5.6% |
| Total Local Funding | 3,581,156 | 70.9% |
Project Description
This project includes a traffic study to evaluate lowering the speed limit, filling in the remaining gaps in multimodal improvements, and finishing the corridor with additional traffic calming elements to effectively manage speeds. A signal is being proposed at Eastmont.
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||