The Jones/John Liner/Trail Road Corridor Project is a multi-phased project that will create an alternative east-west route to State Route (SR) 20 relieving congestion and providing capacity to accommodate current and future commercial and industrial growth.
Projects — TIB Project Information
TIB Project Information
City of Sedro Woolley's JonesJohn Liner RR Undercrossing
8-2-126(014)-1
8-2-126(014)-1
JonesJohn Liner RR Undercrossing
Reed St to 100ft w/o Sapp Rd
FY 2026 Urban Arterial Program
Current Phase : Design
Total TIB Funding : $2,149,055
County: Skagit | Legislative District: 39 | Project Length: 0.21 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
Lead Agency | SEDRO WOOLLEY |
Funding Year | 2026 |
Program | UAP |
Current Phase | Design |
Legislative District | 39 |
Congressional District | 2 |
Federal Route Number | 7390 |
Project Length | 0.21 mi. |
ADT | 712 |
Functional Class | Minor |
Type of Work | New Location |
Project Contact | William Bullock |
Contact Email | bbullock@sedro-woolley.gov |
TIB Engineer | Chris Langhoff |
Last Payment Date | |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2029 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2025 | 01/29/2025 |
Bid Auth. Approval | 01/31/2026 | |
Construction Approval | 02/28/2026 | |
Project Closeout | 10/31/2026 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 332,395 | 393,200 |
Right of Way | 59,175 | 70,000 |
Total Design | 391,570 | 463,200 |
Construction Engineering | 159,857 | 189,100 |
Construction Contract | 1,597,628 | 1,891,000 |
Other Construction | 0 | 0 |
Total Construction | 1,757,485 | 2,080,100 |
Total TIB Funding | 2,149,055 | 2,543,300 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SEDRO WOOLLEY | 394,245 | 15.5% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 394,245 | 15.5% |
Project Description
The Jones/John Liner Railroad Undercrossing is a new road (1100 feet) across unimproved right of way. It will consist of one 11-foot travel lane in each direction, curb/gutter on both sides, a three-foot buffer strip and ten-foot multi-use path on the north side, five-foot sidewalk on the south side, redesign the drainage ditch and replace with a modern storm system, and install street lighting in key locations.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Relieves congestion;
- Removes ADA barriers
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |