'The 204th St and 77th Ave intersection is in an area that was farms and pastures 30 years ago. As this area grew, 204th St became a primary E-W route connecting SR-9 to east Arlington and unincorporated Snohomish Co. This intersection is currently a minor-leg stop controlled intersection with 204th St as the major leg. A new development, Park 77 Apartments, immediately south of this intersection is nearing completion, many of the units are occupied with new residents. There is already a visual increase in pedestrian traffic crossing 204th St to access grocery and other stores on the north side of the road. A traffic study predicted that the apartment complex will generate 710 new daily trips with 71 new PM peak-hour trips. The Arlington community has already witnessed two fatal accidents at the intersection, one in 2010 and another in 2017, and does not want to see another fatal accident at this intersection. '
Projects — TIB Project Information
TIB Project Information
City of Arlington's 204th Street Roundabout
8-1-817(007)-1
8-1-817(007)-1
204th Street Roundabout
77th Ave NE
FY 2020 Urban Arterial Program
Current Phase : Audit
Total TIB Funding : $1,617,000
County: Snohomish | Legislative District: 39 | Project Length: 0.10 | TIB Engineer: Greg Armstrong | Last Payment Date: 06/28/2021
Project Information
Lead Agency | ARLINGTON |
Funding Year | 2020 |
Program | UAP |
Current Phase | Audit |
Legislative District | 39 |
Congressional District | 2 |
Federal Route Number | 2736 |
Project Length | 0.10 mi. |
ADT | 8,081 |
Functional Class | Minor |
Type of Work | Safety |
Project Contact | James Kelly |
Contact Email | jkelly@arlingtonwa.gov |
TIB Engineer | Greg Armstrong |
Last Payment Date | 06/28/2021 |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2018 | |
Delayed Project Date | 07/01/2023 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/04/2019 | 02/04/2019 |
Bid Auth. Approval | 05/07/2020 | 04/24/2020 |
Construction Approval | 05/21/2020 | 05/28/2020 |
Project Closeout | 06/15/2021 | 06/14/2021 |
Audit Date | 06/28/2021 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 153,720 | 254,806 |
Right of Way | 170,073 | 311,634 |
Total Design | 323,793 | 566,440 |
Construction Engineering | 158,953 | 305,409 |
Construction Contract | 1,134,254 | 2,623,799 |
Other Construction | 0 | 117,372 |
Total Construction | 1,293,207 | 3,046,580 |
Total TIB Funding | 1,617,000 | 3,613,020 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
ARLINGTON | 1,014,231 | 28.1% |
WSDOT Funding | 0 | 0.0% |
Water Utility | 259,937 | 7.2% |
Storm Utility | 406,852 | 11.3% |
Snohomish County | 315,000 | 8.7% |
Total Local Funding | 1,996,020 | 55.3% |
Project Description
'The proposed solution to the problem at this intersection would be to design and construct intersection improvements that will allow for the safe movement of vehicles, bicycles, and pedestrians while also accommodating transit stops. The only solution that meets all of these goals is the installation of a roundabout. The City evaluated installing a 4-way stop controlled intersection but the control would cause east bound traffic to back-up into SR-9.Arlington evaluated options for this intersection with a traffic consultant, a copy of the planning level roundabout design is included with this grant application (Att #2). With this design, vehicles will be slowed by the roundabout configuration and allow for the safe movement from all four legs of the intersection. Pedestrian facilities will be on all four corners and connect to existing sidewalks. Crosswalks will be installed on all intersection legs and include safe refuge islands at all crosswalk midpoints. The intersection improvement will expand the existing NW and SE corner bus stops.This grant request is to fund the design, ROW procurement, and construction of a roundabout at the 204th St and 77th Ave intersection. The community is in full support of a safer intersection
Existing Condition
Project Benefits
- Improves safety;
- Improves vehicle and pedestrian access;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |