The State Avenue corridor between 100th St NE and 104th Pl NE consists of an existing three lane section with varying widths of paved shoulder. State Avenue serves as a parallel route to Interstate 5 and is a primary corridor providing north / south travel the full length of the City. The section between 100th St NE and 116th St NE is the final remaining segment to be widened to build out the corridor. The section between 100th St NE and 104th Pl NE is one of the more challenging sections as it requires replacement of a culvert at Quil Ceda Creek with a short-span bridge. This section of the corridor currently lacks necessary pedestrian facilities, illumination and adequate capacity and, is a bottleneck along this critical arterial corridor.
Projects — TIB Project Information
TIB Project Information
City of Marysville's State Avenue
8-1-143(009)-1
8-1-143(009)-1
State Avenue
100th St NE to 104th Pl NE
FY 2018 Urban Arterial Program
Current Phase : Audit
Total TIB Funding : $6,620,832
County: Snohomish | Legislative District: 38 | Project Length: 1.00 | TIB Engineer: Greg Armstrong | Last Payment Date: 12/15/2022
Project Information
Lead Agency | MARYSVILLE |
Funding Year | 2018 |
Program | UAP |
Current Phase | Audit |
Legislative District | 38 |
Congressional District | 2 |
Federal Route Number | 2691 |
Project Length | 1.00 mi. |
ADT | 17,400 |
Functional Class | Principal |
Type of Work | Minor Widening |
Project Contact | Jeff Laycock, PE |
Contact Email | jlaycock@marysvillewa.gov |
TIB Engineer | Greg Armstrong |
Last Payment Date | 12/15/2022 |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/18/2016 | |
Delayed Project Date | 07/01/2021 | |
DAHP Assessment Date | 10/07/2019 | |
Predesign Approval | ||
Design Approval | 01/01/2017 | 12/19/2016 |
Bid Auth. Approval | 11/01/2019 | 10/08/2019 |
Construction Approval | 11/22/2019 | 11/22/2019 |
Project Closeout | 12/31/2022 | 11/29/2022 |
Audit Date | 12/15/2022 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 803,154 | 2,262,636 |
Right of Way | 467,678 | 1,416,811 |
Total Design | 1,270,832 | 3,679,447 |
Construction Engineering | 414,582 | 987,312 |
Construction Contract | 4,585,418 | 12,270,262 |
Other Construction | 0 | 2,176 |
Total Construction | 5,000,000 | 13,259,750 |
Funding Increase | 350,000 | |
Total TIB Funding | 6,620,832 | 16,939,197 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MARYSVILLE | 10,318,365 | 60.9% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 10,318,365 | 60.9% |
Project Description
The Project proposes to widen the corridor to five-lanes for added capacity, provide pedestrian facilities along both sides of the roadway, relocate transit stops to improve safety, replace the existing culvert at Quil Ceda Creek with a short-span bridge, construct storm drainage facilities improvements to address storm water runoff, and associated utility improvements including replacement and relocation of City-owned and franchise utilities. In addition, the Project will improve safety at the 100th Street NE intersection by replacing Emergency Vehicle (EV) detection and adding pedestrian crossing push-button and display heads.
Existing Condition
Project Benefits
- Improves safety;
- Improves mobility;
- Completes gap;
- Increases access control;
- Utilizes low-energy lighting
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |