City of Bothell's Meridian Avenue Roundabout

8-1-114(009)-1

8-1-114(009)-1
Meridian Avenue Roundabout

240th St Roundabout

FY 2025 Urban Arterial Program
Current Phase : Audit
Total TIB Funding : $693,951

County: King/Snohomish   |   Legislative District: 1   |   Project Length: 0.40   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 12/12/2024

Project Information

Lead Agency BOTHELL
Funding Year 2025
Program UAP
Current Phase Audit
Legislative District 1
Congressional District 1
Federal Route Number 2567
Project Length 0.40 mi.
ADT 14,054
Functional Class Minor
Type of Work Traffic Control
Project Contact Allyx Copeland
Contact Email allyx.copeland@bothellwa.gov
TIB Engineer Greg Armstrong
Last Payment Date 12/12/2024
Cultural Resource Assessment Section 106

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 01/01/2025  
DAHP Assessment Date   08/18/2022
Predesign Approval
Design Approval 02/01/2024 12/14/2023
Bid Auth. Approval 03/05/2024 02/23/2024
Construction Approval 04/05/2024 04/09/2024
Project Closeout 12/31/2024 12/05/2024
Audit Date   12/12/2024
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 111,604 259,936
Construction Contract 688,396 1,746,172
Other Construction 0 0
Total Construction 800,000 2,006,108
     
Funding Surplus - 106,049  
Total TIB Funding 693,951 2,006,108

Local Funding Partners

Funding Amount Percent
BOTHELL 27,250 1.5%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
Federal Funding  1,284,907 68.5%
Total Local Funding 1,312,157 70.0%

Project Description

This project will improve safety of the Meridian Avenue and 240th Street by adding the following improvements a roundabout, curb ramps, pedestrian paths, raised center medians, crosswalks, pedestrian islands, drainage and bio infiltration, street illumination, and signage.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.