TIB Project Information

City of Federal Way's S 288th Street

8-1-113(013)-1

8-1-113(013)-1
S 288th Street

16th Ave S to 34th Ave S

FY 2022 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $2,081,535

County: King   |   Legislative District: 30   |   Project Length: 1.13   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 12/06/2024

Project Information

Lead Agency FEDERAL WAY
Funding Year 2022
Program UAP
Current Phase Construction
Legislative District 30
Congressional District 9
Federal Route Number 1150
Project Length 1.13 mi.
ADT 15,000
Functional Class Minor
Type of Work Safety
Project Contact Christine Mullen
Contact Email Christine.mullen@federalwaywa.gov
TIB Engineer Greg Armstrong
Last Payment Date 12/06/2024
Cultural Resource Assessment CRA & BER

Project Schedule

  Target Date Actual Date
Project Selection Date   11/20/2020
Delayed Project Date 07/01/2025  
DAHP Assessment Date   02/08/2023
Predesign Approval
Design Approval 01/15/2021 01/20/2021
Bid Auth. Approval 01/10/2025 12/23/2024
Construction Approval 03/13/2025 03/13/2025
Project Closeout 12/31/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 327,160 355,000
Right of Way 37,037 151,000
Total Design 364,197 506,000
     
Construction Engineering 274,692 406,199
Construction Contract 1,361,111 2,266,774
Other Construction 0 0
Total Construction 1,635,803 2,672,973
     
Funding Increase 81,535  
Total TIB Funding 2,081,535 3,178,973

Local Funding Partners

Funding Amount Percent
FEDERAL WAY 997,438 31.4%
WSDOT Funding 0 0.0%
Bike/Ped Safety  100,000 3.1%
 
 
 
 
 
 
 
Total Local Funding 1,097,438 34.5%

Project Description

The City proposes to provide a continuous bicycle and pedestrian route between Pacific Hwy S and Military Road S, meeting all ADA requirements. The project would include the construction of 3 mid-block pedestrian crosswalks with pedestrian refuge islands and Rectangular Rapid Flashing Beacons, replacement of the traffic signal at Military Road S to comply with MUTCD and ADA requirements with the revised channelization, and traffic signal modifications at SR 99 to improve efficency and reduce delays for non-motorized users.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.