City of Auburn's Auburn Way S Widening

8-1-105(038)-1

8-1-105(038)-1
Auburn Way S Widening

Hemlock St to Poplar St

FY 2025 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $3,187,534

County: King   |   Legislative District: 31   |   Project Length: 0.45   |   TIB Engineer: Greg Armstrong   |   Last Payment Date:

Project Information

Lead Agency AUBURN
Funding Year 2025
Program UAP
Current Phase Construction
Legislative District 31
Congressional District 8
Federal Route Number 0164
Project Length 0.45 mi.
ADT 24,500
Functional Class Principal
Type of Work Major Widening
Project Contact Jeffrey Bender
Contact Email jbender@auburnwa.gov
TIB Engineer Greg Armstrong
Last Payment Date
Cultural Resource Assessment Section 106

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 01/01/2025  
DAHP Assessment Date   03/08/2023
Predesign Approval
Design Approval 02/01/2024 01/08/2024
Bid Auth. Approval 12/15/2024 12/11/2024
Construction Approval 02/07/2025 02/13/2025
Project Closeout 06/30/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 170,542 532,326
Construction Contract 3,138,490 7,168,191
Other Construction 0 0
Total Construction 3,309,032 7,700,517
     
Funding Surplus - 121,498  
Total TIB Funding 3,187,534 7,700,517

Local Funding Partners

Funding Amount Percent
AUBURN 907,896 11.8%
WSDOT Funding 0 0.0%
Federal STP Grant  3,605,087 46.8%
 
 
 
 
 
 
 
Total Local Funding 4,512,983 58.6%

Project Description

This project widens Auburn Way S (SR 164) from Hemlock Street to Poplar Street SE to provide a five-lane section with a center turn lane/median.The project also implements specific improvements improving the safety of school bus stops adding sidewalks to accommodate non-motorized travel, installing access control to improve safety and operations, and improving transit facilities. A pedestrian crossing, enhanced with an RRFB is proposed at the east end of the improvements after the transition back to the existing three-lane section to provide pedestrian circulation and access to transit. The project will also realign Poplar St SE to the west of the existing intersection with SR 164 to provide adequate sight distance at the intersection.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments