Town of Cathlamet's Butler Street Reconstruction

6-W-979(007)-1

6-W-979(007)-1
Butler Street Reconstruction

Main St(SR 409) to Una Ave

FY 2026 Small City Arterial Program
Current Phase : Design
Total TIB Funding : $341,387

County: Wahkiakum   |   Legislative District: 19   |   Project Length: 0.05   |   TIB Engineer: Chris Langhoff   |   Last Payment Date:

Project Information

Lead Agency CATHLAMET
Funding Year 2026
Program SCAP
Current Phase Design
Legislative District 19
Congressional District 3
Federal Route Number 9999
Project Length 0.05 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Reconstruction
Project Contact Jacquelyn Gribble
Contact Email projectmanager@townofcathlamet.com
TIB Engineer Chris Langhoff
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 01/01/2025 12/17/2024
Bid Auth. Approval 01/01/2026
Construction Approval 02/01/2026
Project Closeout 12/01/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 36,506 36,506
Right of Way 25,000 25,000
Total Design 61,506 61,506
     
Construction Engineering 36,506 36,506
Construction Contract 243,375 243,375
Other Construction 0 0
Total Construction 279,881 279,881
     
Total TIB Funding 341,387 341,387

Local Funding Partners

Funding Amount Percent
CATHLAMET 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

The roadway will be rebuilt in its current location. The existing extruded curb on the easterly side of the road will be replaced with curb and gutter. The existing curb and walkway on the westerly side of the road will be replaced with curb and gutter and accessible sidewalks and driveway entrances. Minor storm drainage improvements will be added to direct runoff to the existing system.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments